Slipform advances Kishorn floating foundation factory plans

Slipform advances Kishorn floating foundation factory plans

Slipform Engineering has advanced plans for its Kishorn production facility. Manufacturing simulations have examined the proposed production of up to 36 concrete floating wind foundations annually, with smaller-scale equipment trials planned at Hunterston from January 2027.


IN Brief:

  • Slipform Engineering is developing plans for a factory capable of manufacturing 36 floating concrete foundations annually.
  • NMIS has assessed production capacity, costs, workforce requirements, and manufacturing bottlenecks.
  • A demonstration facility at Hunterston is scheduled to open in January 2027, ahead of any confirmed full-scale factory investment.

Slipform Engineering has progressed its proposals for a concrete floating offshore wind foundation factory at Kishorn in the Scottish Highlands, following manufacturing research intended to assess how the facility could operate at scale.

The proposed Slipform Engineering Slip4Wind factory would have the capacity to manufacture up to 36 floating foundations annually. Each foundation would weigh approximately 20,000 tonnes, with the completed structures intended to support more than 500MW of offshore wind generating capacity each year.

The National Manufacturing Institute Scotland (NMIS) has examined the proposed manufacturing process through the Offshore Wind Growth Partnership’s SmartStart Manufacturing Programme. The research assessed production capacity, costs, workforce requirements, and opportunities to improve the organisation of manufacturing activities before major investment decisions are made.

The work addresses a fundamental problem in producing large floating foundations: moving a partly completed structure weighing thousands of tonnes between manufacturing stations requires substantial equipment, supporting infrastructure, and operating space.

Slipform Engineering proposes keeping the foundations stationary during construction. A specially designed gantry system would instead move manufacturing equipment around each structure, allowing the foundation to be built in position before it is transferred into the water.

This reverses the conventional relationship between a manufactured component and the equipment used to assemble it. Rather than bringing a large structure to successive production stations, the necessary machinery and personnel would move around the structure as construction progresses.

The approach draws on slipforming, an established concrete construction technique that allows formwork to advance progressively as concrete is placed. The method can be used to construct substantial concrete walls and other structural elements with a controlled, continuing production sequence.

Successful slipforming depends on matching the movement of the formwork to the condition of the concrete, the rate of placement, reinforcement requirements, and the geometry being constructed. Moving too quickly or interrupting the sequence can affect the quality and consistency of the finished structure.

Applying these principles to offshore wind foundations introduces further demands arising from their size and construction sequence. The production system must accommodate large volumes of concrete and reinforcement while providing access for placement, inspection, and other activities.

The company intends its moving gantry to reduce the amount of internal transportation required within the proposed factory. A completed foundation could then be transferred towards the water without repeatedly moving the structure during earlier manufacturing stages.

The potential benefit is a reduction in some of the handling operations and associated infrastructure needed to move extremely heavy components. However, the final transport method, gantry dimensions, structural loads, and factory layout have not been established in the published project information.

The manufacturing research therefore concentrated on the relationship between production activities and the resources required to complete them. NMIS used discrete event simulation to model operations and examine how changes in workforce arrangements and production sequencing could affect output.

Discrete event simulation represents a manufacturing process as a sequence of activities occurring over time. It allows engineers to examine the interaction between resources, equipment availability, processing durations, and delays without physically operating a complete production facility.

The modelling is particularly relevant where several operations depend on one another. If reinforcement installation, concrete placement, or another activity takes longer than expected, equipment and labour scheduled for subsequent tasks may remain idle.

A delay at one stage can therefore influence output across the production system, even where other equipment is capable of working more quickly. Identifying these constraints during design allows alternative arrangements to be assessed before substantial capital expenditure is committed.

NMIS examined workforce numbers and shift patterns, identifying opportunities to improve efficiency through more flexible labour arrangements and the development of multi-skilled teams.

Cross-training can increase the availability of personnel for different production activities, although specialist tasks must still be performed by people with the appropriate competence and authorisation. Workforce flexibility cannot remove the engineering and safety requirements governing the operation of large construction equipment.

The research has informed a phased development plan covering infrastructure, regulation, investment, and skills. These areas will influence whether the proposed annual output is achievable under practical manufacturing conditions.

The 36-foundation capacity remains a proposal rather than a demonstrated production rate. Similarly, the potential 500MW-plus annual contribution represents the generating capacity that foundations produced by the factory could support, not electricity generated by the manufacturing site or an existing portfolio of installed turbines.

Alongside its Kishorn proposals, Slipform Engineering is developing a demonstration, research, development, and training facility at Hunterston in North Ayrshire. The smaller facility is expected to open in January 2027.

Hunterston will provide an opportunity to test a reduced-scale version of the gantry system and examine different concrete materials. The work will help establish how elements of the proposed production process behave before equipment and methods are expanded to full industrial scale.

Concrete material selection will be important because floating offshore foundations must satisfy structural and durability requirements associated with prolonged exposure to marine conditions. Their performance depends on the complete structural design, material characteristics, production quality, and environmental exposure.

The reported plans do not specify the final concrete mix, reinforcement arrangement, or certification status of the proposed foundations. Those details will require further technical development and should not be inferred from the factory’s intended output.

NMIS has also connected the company with Ayrshire College to explore workforce development. Manufacturing at the proposed scale would require training arrangements suited to the operation of the equipment and the processes used to produce the concrete structures.

The wider factory proposal remains subject to investment and implementation decisions. No confirmed construction contract, capital expenditure commitment, or opening date has been disclosed for the Kishorn facility.

The immediate milestone is the planned opening of the Hunterston demonstration site in January 2027. Testing there will provide a further opportunity to assess the production approach before Slipform Engineering progresses towards a full-scale factory designed around its proposed annual output.



  • Lodge Hill interchange completion moves into spring

    Lodge Hill interchange completion moves into spring

    Completion of Oxfordshire’s Lodge Hill interchange has moved into spring. The A34 improvement programme will continue through December, with outstanding roundabout, slip road, and access works following changes to the construction sequence.


  • Dublin drainage project enters preliminary construction

    Dublin drainage project enters preliminary construction

    Preliminary works have begun on Dublin’s new wastewater infrastructure project. Greater Dublin Drainage will include a treatment plant, orbital sewer, pumping station, and marine outfall, with main construction planned for 2028 and completion targeted for 2031.