HS2 begins bulk excavation at Euston

HS2 begins bulk excavation at Euston

HS2 has begun major excavation beneath its future Euston station. Rail freight will transport up to 170,000 tonnes of material from the site, including earlier trial movements, with more than 10,000 lorry journeys expected to be avoided.


IN Brief:

  • Mace Dragados has begun bulk excavation to approximately seven metres beneath the existing Euston site.
  • Around 35,000 tonnes have already been transported during trials, with a further 135,000 tonnes expected over ten months.
  • GB Railfreight will operate up to two trains daily, each carrying approximately 715 tonnes to Bedfordshire for reuse.

HS2 has begun bulk excavation at Euston, introducing a larger rail freight operation to remove construction material from the station site while limiting heavy goods vehicle movements through central London.

The HS2 station construction partner, the Mace Dragados joint venture, is excavating to a depth of approximately seven metres below existing ground level, where platforms for the new high-speed railway will be constructed. Material is being transported by GB Railfreight from a loading facility beside the disused Track 17 at Euston.

Up to 170,000 tonnes of excavated material are expected to be moved by train across the programme. The total includes approximately 35,000 tonnes already transported during trials between February and September 2026, with a further 135,000 tonnes planned over the next ten months.

The railway operation is expected to avoid more than 10,000 heavy goods vehicle journeys that would otherwise have been required to move the material from the construction site by road. The material is being taken to Forders Sidings in Bedfordshire for reuse at the Stewartby Brickworks development.

Bulk excavation is a substantial step in preparing the station site. The work must create the space required for future railway infrastructure while remaining compatible with existing structures, surrounding development, and the operational railway at Euston.

Excavation at an established city centre station creates different constraints from earthworks on an open construction site. Access for plant, the movement of excavated material, temporary works, and the position of surrounding infrastructure all affect the sequence in which ground can be removed.

The excavation method must also accommodate the engineering requirements of the future station. Removing ground changes the loads acting on adjacent structures and supporting elements, making the progression of excavation dependent on the relevant structural arrangements and monitoring requirements.

The published construction update does not specify the complete excavation support system or detailed temporary works design. Those arrangements remain separate from the confirmed depth and the announcement that bulk excavation has begun.

Material removal is a major part of the operation because the excavation programme cannot progress efficiently if the site lacks the capacity to handle spoil. Excavators and loading equipment must be coordinated with the transport system so that removed material does not accumulate beyond available storage or handling capacity.

Using rail freight changes the scale of individual transport movements. Each train can carry approximately 715 tonnes, which HS2 equates to around 45 heavy goods vehicle loads. The trains are operated by GB Railfreight and comprise two locomotives with up to 12 wagons.

Up to two trains a day will be used during the main excavation programme. Their movements must be accommodated alongside passenger services, requiring coordination between the construction team, freight operator, and organisations responsible for the existing railway infrastructure.

The initial trials demonstrated that the arrangement could be operated successfully. They also allowed HS2 and its partners to assess loading and train movements before increasing the volume transported during the principal excavation phase.

Rail capacity alone does not determine how much material can be removed. The loading facility must receive spoil at an appropriate rate, and each train must be loaded within the time available before its scheduled departure.

Excavation productivity and freight availability are therefore linked. A delay in the excavation sequence may reduce the material ready for transport, while a disrupted train movement may affect the handling and storage arrangements required on site.

The new loading point makes use of railway infrastructure at Euston that is no longer required for its previous passenger function. This provides a means of transferring material directly from the construction operation onto freight trains without first transporting it through the surrounding streets.

The destination is also part of the material management strategy. Excavated material will be taken to the Stewartby Brickworks development, where it is intended for reuse rather than disposal through an unspecified waste route.

The current information does not identify the precise engineering use or classification of each material type. Recovery and reuse remain subject to the characteristics of the excavated material and its suitability for the receiving development.

Rail freight also reduces the number of construction vehicles travelling through the road network near Euston. Camden is a constrained urban environment where heavy vehicle movements interact with pedestrians, cyclists, local traffic, businesses, and residential streets.

Avoiding thousands of lorry journeys can reduce the traffic associated with excavation, although the actual benefit will depend on the quantity moved and the number of road movements displaced as the programme proceeds.

The environmental comparison requires similar precision. HS2 identifies a general estimate that rail freight can produce up to 76% fewer carbon dioxide emissions than equivalent road freight movements.

That figure is not a measured carbon saving for this excavation programme. Calculating a project-specific reduction would require the actual distances, train and vehicle loads, fuel use, handling operations, and any onward transport movements to be considered.

The transition from trial movements to the main excavation operation was highlighted during a visit on 16 November by Rail Minister Lord Hendy and Camden Council leader James Slater.

The railway is also being considered for further construction logistics activity. Track 17 is expected to remain available until early 2029, providing a potential route for additional freight movements associated with development of the wider Euston site.

Any extension of that use would depend on future construction requirements and agreements with the organisations responsible for the railway. It should not be treated as an approved commitment to transport additional quantities beyond the currently identified programme.

The next ten months will determine how effectively the excavation and freight operations can be maintained together. With approximately 35,000 tonnes already moved, the principal remaining task is transporting the planned further 135,000 tonnes while construction advances towards the level of the future station platforms.



  • Glasgow Broadway Studios reaches practical completion

    Glasgow Broadway Studios reaches practical completion

    Glasgow’s Broadway Studios student development has now achieved practical completion. The 432-bed building, delivered by McAleer & Rushe for MRP, incorporates air-source heat pumps, has an EPC A rating, and is targeting BREEAM Excellent certification.


  • Lodge Hill interchange completion moves into spring

    Lodge Hill interchange completion moves into spring

    Completion of Oxfordshire’s Lodge Hill interchange has moved into spring. The A34 improvement programme will continue through December, with outstanding roundabout, slip road, and access works following changes to the construction sequence.