IN Brief:
- Kane will deliver the full design and build building services package in partnership with main contractor Sisk.
- The refurbishment and extension will provide more than 200,000 sq ft of Grade A office accommodation.
- Prefabricated installations will support a wider construction programme targeting material recovery, reduced embodied carbon, and completion in late 2027.
Building services contractor Kane Group has secured a £40m mechanical, electrical, and plumbing contract for the refurbishment and extension of 171 Victoria Street in Westminster, London, where existing retail premises will remain operational throughout construction.
Kane will deliver the full design and build building services package in partnership with main contractor Sisk, incorporating prefabricated components manufactured away from the construction site. The redevelopment of the former John Lewis headquarters will provide more than 200,000 sq ft of Grade A office accommodation upon completion.
Sisk is delivering the project for Kirkglade Ltd, with TP Bennett responsible for architectural design and Savills and Core Five involved in project management. Completion is scheduled for the final quarter of 2027.
The redevelopment incorporates selective dismantling of existing building elements, allowing materials to be recovered for reuse or recycling. Sisk has identified structural steelwork, concrete, and approximately 500 stainless steel window frames and associated glazing units within the material recovery programme.
Retaining substantial elements of the building introduces different constraints on the design and installation of its replacement mechanical and electrical infrastructure. Existing structural dimensions, floor heights, service openings, and plant accommodation will influence how the new installations can be distributed.
The former headquarters was designed around the requirements of a single corporate occupier. Its conversion into more flexible commercial accommodation requires building services capable of supporting different tenancy arrangements and potentially varying occupancy patterns across individual floors.
Mechanical ventilation, electrical distribution, heating and cooling systems, and associated controls must be coordinated with those arrangements. Changes to the internal layout can also affect fire compartmentation and the distribution of services through retained structural elements.
Kane’s use of off-site manufacturing will allow selected assemblies to be produced under factory conditions before delivery to Westminster. Depending on the final design, prefabricated building services can incorporate coordinated pipework, distribution equipment, support structures, and mechanical plant assemblies.
Manufacturing those components away from the building can allow assembly and inspection to proceed concurrently with structural refurbishment. It can also reduce the space required for material preparation and individual installation activities within the construction area.
The approach depends on establishing reliable dimensional information before components are released for manufacture. Assemblies designed around inaccurate information concerning retained structural elements or existing services may require modification before installation, reducing the programme advantages associated with prefabrication.
Surveying and design coordination are therefore particularly important in refurbishment projects, where historical drawings may not fully reflect alterations made during the building’s operational life. Access routes must also accommodate the dimensions and weight of completed assemblies, which can differ considerably from those of individual components delivered for conventional site installation.
Maintaining operational retail premises adds another constraint to the replacement of existing building services. Mechanical and electrical infrastructure serving occupied areas may be connected to systems extending through parts of the building undergoing refurbishment.
Where those connections must be transferred, phased installation and commissioning can allow replacement infrastructure to be brought into operation before existing services are removed. Temporary arrangements may be required where the condition or configuration of retained systems prevents a direct changeover.
The specific equipment selected for the Victoria Street installation has not been disclosed. Earlier redevelopment proposals identified an all-electric building services strategy incorporating air source heat pumps, although the final specifications and equipment capacities remain subject to the detailed design.
The performance of electrically driven heating systems depends partly on their integration with distribution equipment and the thermal characteristics of the building envelope. Lower operating temperatures can improve heat pump efficiency, but existing distribution systems and terminal units may require modification to provide sufficient heating capacity under those conditions.
The refurbishment’s wider façade improvements will also influence heating and cooling requirements. Sisk has specified lower embodied carbon glazing for the replacement façade, alongside the recovery of existing window assemblies through its dismantling programme.
Construction materials are being addressed through a separate specification incorporating Ecocem’s ACT cement technology. Approximately 1,300 cubic metres of concrete using the technology are expected to be placed at Victoria Street by the end of 2026.
Coordinating the concrete and structural construction programme with the building services design will allow openings, support locations, and equipment installation requirements to be incorporated before individual work areas are completed. This can limit the need for subsequent alterations to structural elements, particularly where prefabricated services require accurately positioned connections.
The £40m appointment brings the design, manufacture, and installation of the building’s replacement mechanical and electrical infrastructure into a single specialist package. Kane’s manufacturing programme will need to remain aligned with Sisk’s construction sequence and the requirements of existing retail occupants as the development progresses towards its scheduled late-2027 completion.