IN Brief:
- Balfour Beatty VINCI has completed the first half of the new A45 overbridge near Bickenhill.
- The structure incorporates 46 piles, 13 prestressed concrete beams, and a bridge deck weighing approximately 2,000 tonnes.
- A December traffic switchover will allow the remaining construction to proceed, with the final road alignment expected in summer 2028.
Construction of a new overbridge carrying the A45 above the HS2 railway has reached its halfway point, following completion of the first section of the structure near Bickenhill in the West Midlands.
HS2 construction partner Balfour Beatty VINCI has completed the eastern section of the Coventry Road overbridge after approximately 11 months of work. The structure is being built in two halves to maintain highway traffic between Stonebridge Island and Junction 6 of the M42 while the railway corridor is excavated beneath the road.
The first section incorporates 46 piles reaching depths of up to 23 metres, pile caps supporting the structure, and a bridge deck weighing approximately 2,000 tonnes. Engineers installed 13 prestressed precast concrete beams during the summer to support the 37-metre span, followed by 13 parapet units.
The bridge will ultimately carry road traffic over a four-track section of the new railway approaching Interchange Station. Its construction requires changes to the existing highway arrangement while maintaining access along a heavily used route between the strategic road network and nearby communities.
A top-down construction method has been adopted to accommodate these constraints. Under this approach, structural support is established before excavation progresses beneath the road, allowing sections of the bridge to be constructed while maintaining the highway corridor above.
The sequence differs from a conventional bridge project in which the entire road might be closed, the ground excavated, and a completed structure built across the resulting opening. At Bickenhill, the contractor must retain sufficient highway capacity while creating the bridge and railway cutting in successive stages.
Deep piles transfer structural loads into suitable ground beneath the excavation. Their performance depends on the ground conditions and foundation design, while pile caps distribute the forces imposed by the bridge structure into the supporting piles.
Once the foundation and supporting elements are established, excavation beneath the future deck can progress without removing the load-bearing system required for the road above. The sequence also introduces demanding temporary works and monitoring requirements because ground removal changes the conditions surrounding an already constructed structure.
The use of precast concrete beams provides another means of managing construction activity within the restricted corridor. Components can be manufactured under controlled conditions before being transported to the site and lifted into their final positions.
Prestressing introduces compression into the concrete, helping control tensile stresses when the beams carry their intended loads. Their behaviour within the completed bridge depends on the connections, supports, deck arrangement, and loading conditions incorporated into the structural design.
The 13 beams installed during the summer support the first 37-metre span. Parapet units provide part of the bridge’s edge protection arrangement, although the complete highway also requires the appropriate surfacing, containment systems, drainage, and associated infrastructure.
The first half is now being prepared for a traffic switchover. Waterproofing and highway works must be completed before motorists can use the newly constructed section, with the revised traffic arrangement releasing the remaining area for construction.
From Monday 7 December, overnight and weekend closures will be introduced to facilitate the change. The works are being coordinated with National Highways because the A45 forms part of a strategic route serving Birmingham Airport, the National Exhibition Centre, and the wider motorway network.
A temporary traffic arrangement must accommodate the load and movement requirements of road users while maintaining safe separation from the active construction site. The positioning of barriers, temporary markings, work access points, and changes in carriageway alignment determines how much space contractors can safely occupy.
Once traffic is transferred, Balfour Beatty VINCI will begin the second half of the overbridge. That phase will follow a similar structural sequence while excavation continues to establish the railway alignment beneath the completed sections.
The interaction between road traffic and railway construction creates competing demands on the project programme. Highway works must reach a condition suitable for temporary use before the next excavation area can be released, while the foundation and bridge construction must remain compatible with the space required for the eventual railway cutting.
Heavy lifting operations introduce another constraint. Precast beams and other structural components have to be installed using equipment positioned within the available construction area, with lifting plans accounting for loads, working radii, ground support, and exclusion zones.
The precise size and positioning of the lifting equipment have not been confirmed in the current project update. Those details are consequently separate from the verified quantities of installed piles, beams, and parapet units.
The railway corridor beneath the bridge will lead towards HS2’s Interchange Station, approximately one mile away. The station is designed with two 425-metre island platforms providing four platform faces, accommodating trains moving through the wider West Midlands section of the route.
The overbridge is one of several substantial civil engineering structures required to accommodate the new railway alongside existing transport infrastructure. Other HS2 works are progressing around Birmingham, including the separate Curzon approaches, although their structures and construction programmes are independent of the A45 crossing.
Following the completion of both halves, permanent highway works will include lighting, kerbs, drainage, and the final carriageway arrangement. These installations must be integrated with the bridge structure and adjoining road network before the temporary traffic layout can be replaced.
Structural completion is expected by the end of 2027, with the finished road alignment scheduled to enter use in summer 2028. The bridge’s present halfway milestone therefore precedes several further stages of excavation, structural construction, and highway completion.
The immediate task is the December traffic transfer. Its successful completion will allow the second construction area to be occupied while motorists continue using the first finished section of the new overbridge.