IN Brief:
- The Fairfax Road travel hub opens on 24 November with more than 300 parking spaces.
- The old Longfield car park closes permanently on 25 November to release land for site investigations.
- DSM Demolition is working at the former centre while surrounding shops and services remain accessible.
Bury Council will open the Prestwich Travel Hub on Fairfax Road on Tuesday 24 November, enabling the existing Longfield Centre car park to close permanently the following day. The change gives demolition and investigation teams access to another part of the town centre site being prepared for the wider £100m-plus Prestwich Village redevelopment. Works to remove the former shopping centre have already begun; the release of the car park is a further stage in making the central site available for redevelopment.
The travel hub provides more than 300 parking spaces, including accessible provision and electric vehicle charging, as well as cycle facilities. Bury Council owns the building, with APCOA appointed to operate it. Opening the replacement parking facility before removing the Longfield spaces allows the council to maintain town centre access while land needed for investigations and construction preparation is taken out of public use.
The Longfield car park is scheduled to close on Wednesday 25 November. Notices have been displayed ahead of the change, and further signs and site barriers will mark the area where work is taking place. The council has identified investigations and preparations as the immediate purpose of the closure, but it has not published a programme of individual ground investigation activities or announced the findings of any new surveys. The date is consequently a confirmed change in site access, rather than a confirmed foundation start.
Investigation works on a former commercial site can involve checking the position of buried services and existing foundations, alongside sampling ground conditions needed for excavation and drainage design. Their scope must follow the available records and the areas that become accessible as buildings and surfaces are removed. Although those are ordinary requirements when planning a new development, the council has not specified particular boreholes, contamination findings or ground improvement measures for the former car park.
Specialist contractor DSM Demolition is undertaking the removal of the old Longfield Shopping Centre. The operation is being carried out within a working village centre rather than on an isolated construction plot, requiring continuing access to neighbouring premises. Shops on Poppythorn Lane and businesses in the Radius building are to remain open and accessible throughout the work. Routes for pedestrians and visitors will therefore have to be maintained around the changing construction boundary.
The £100m-plus regeneration is being delivered through Prestwich Regeneration LLP, the joint venture between Bury Council and developer Muse. The current proposals include a new market hall, a larger village square, retail and leisure accommodation, community facilities, a library and up to 248 homes. Those elements form the subsequent redevelopment programme; they should not be confused with the travel hub, which was developed as an enabling project and is approaching its operational opening.
Providing the parking facility on Fairfax Road first changes how the central site can be used. The existing surface car park sits on land required for the new village centre, while the replacement structure moves parking provision away from the intended public spaces and redevelopment plots. The sequence also helps separate public vehicle movements from the areas available to the demolition contractor. Bury Council has not set out a detailed haulage route or construction traffic plan for the next phase.
The hub has been under construction as an early phase of the regeneration for an extended period. In October, the council outlined the operating arrangements and indicated that the building would open in the autumn once handover and final preparations were complete. Its latest confirmation fixes the opening date at 24 November and the old car park closure at 25 November. That provides a more definite handover point than the earlier indicative programme, without changing the status of the wider scheme.
The new facility has been reported as costing more than £14m, a separate figure from the wider £100m-plus regeneration value. The broader project also has funding support from Greater Manchester programmes, covering different elements of the redevelopment and its enabling work. No updated construction contract value for the market hall or residential buildings has been confirmed in the council’s November update. Nor has a definitive date been given for their main building works to start.
The continuing demolition and forthcoming investigations will determine how the former Longfield site can move into the next construction phase. As the working area expands, safe access for the surrounding businesses and the public remains an immediate operational condition. From 25 November, the former parking area will no longer be available to motorists and will instead form part of the land being prepared for redevelopment; new parking provision will be available at the Fairfax Road hub.



