IN Brief:
- Audits have been completed at 11,141 properties under the Find and Fix programme.
- Major technical defects were recorded in 83% of completed audits, with immediate health and safety risks identified in 10%.
- The programme covers 24,615 eligible properties fitted with external wall insulation.
Almost 9,000 properties fitted with defective external wall insulation remain subject to unresolved remediation work, according to figures published by the Department for Energy Security and Net Zero (DESNZ).
The government’s Find and Fix programme has identified 11,064 properties requiring remedial work following the installation of insulation through the fourth Energy Company Obligation (ECO4) and the Great British Insulation Scheme (GBIS).
As of 4 November 2026, remedial work had been completed and supporting evidence signed off at 2,227 properties, while remediation remained unresolved at 8,983. The published categories overlap, meaning their totals cannot be treated as mutually exclusive.
Of the 11,141 properties audited, 9,288 had major technical faults and 1,111 had defects presenting immediate health and safety risks. The figures represent 83% and 10% of completed audits respectively.
The programme covers 24,615 properties across Great Britain that received external wall insulation through the two schemes and had not previously undergone an audit when Find and Fix commenced in November 2025.
Households associated with 19,216 properties had been contacted by the reporting date. A further 3,194 audits had been booked but were awaiting completion, while access could not be secured or appointments had been declined in 1,756 cases.
The programme follows concerns raised by TrustMark in October 2024 about unusually high levels of non-compliance among solid wall insulation installations. Randomised audits subsequently commissioned by Ofgem identified widespread deficiencies, particularly among properties receiving external wall insulation.
Earlier statistical analysis published by DESNZ found that 92% of sampled external wall insulation installations had major technical non-compliance, while 6% had defects presenting potential health and safety risks. The November 2026 figures measure progress within the subsequent inspection and remediation programme rather than providing a directly comparable randomised sample.
External wall insulation systems reduce heat transfer through existing walls by adding an insulating layer to the external building fabric. Mechanical or adhesive fixings retain the insulation, while reinforcing layers and external finishes protect the assembly from weather exposure and physical damage.
Achieving the intended thermal performance requires continuity of insulation around openings, roof junctions, and adjoining structural elements. Gaps or inadequately insulated connections can create localised thermal bridges, reducing the effectiveness of the installation and increasing the risk of condensation on colder internal surfaces.
Extending the external wall thickness also changes its relationship with existing building components. Window sills, roof overhangs, drainage pipes, and service penetrations may require alterations to maintain effective protection against water ingress.
Where junctions are incorrectly detailed, rainfall can penetrate behind the insulation or its external finish. Moisture trapped within the assembly can subsequently affect the condition of underlying building materials, particularly where the original wall relies on its ability to absorb and release moisture.
The appropriate remediation specification therefore depends on the configuration of the existing wall, the insulation system installed, and the nature of the defects identified during inspection.
Localised failures may require repairs to individual junctions or components, while more extensive defects can necessitate removal and replacement of substantial areas of insulation. Correcting visible damage without addressing the underlying cause of moisture ingress or thermal discontinuity may leave the installation vulnerable to recurring problems.
The government expects the original installers to undertake necessary remediation where possible. TrustMark’s oversight includes recording inspection findings and assessing evidence associated with completed corrective work.
Remediation across thousands of occupied properties requires the coordination of inspection specialists, retrofit coordinators, installers, and certification organisations. Unlike a new installation programme, corrective works must also account for the condition and configuration of materials fitted during earlier construction activity.
The government published proposals in June 2026 to reform consumer protection arrangements across home improvement schemes, following identified weaknesses in the allocation of responsibilities, oversight of installations, and resolution of consumer complaints.
Those reforms address the wider quality assurance framework within which retrofit work is commissioned and delivered. The immediate Find and Fix programme remains focused on identifying defective installations and securing appropriate corrective work.
More than 13,000 properties within the programme’s defined scope had yet to receive a completed audit by 4 November. With only 2,227 properties recorded as having completed and signed-off remediation, substantial inspection and construction work remains outstanding.