IN Brief:
- DfT is consulting on devolving eligible Transport and Works Act order functions in England.
- Mayoral strategic authorities could manage objections, inquiries and final decisions for schemes wholly within their boundaries.
- The consultation closes on 18 December; national rail and cross-boundary applications would remain centrally handled.
The Department for Transport has opened an England-only consultation on transferring responsibility for certain Transport and Works Act orders to mayoral strategic authorities. Under the preferred model, eligible local transport applications would be managed and decided by the mayoral authority in which the proposed scheme sits. Applications affecting the national rail network, or crossing the boundaries of more than one mayoral authority, would remain with central government.
Transport and Works Act orders provide powers to construct, operate or maintain certain transport systems and other specified infrastructure. They are used for schemes such as tramways, light rail, guided busways and eligible railways, as well as some inland waterways, bridges, piers and tunnels. Where the relevant tests are met, an order can authorise works and associated land powers through one statutory route, including compulsory acquisition, temporary possession and changes to highway rights. Ordinary highway projects are not generally promoted through this regime, which is separate from the usual road planning and highways procedures.
The preferred arrangement would apply automatically to every eligible mayoral strategic authority, rather than requiring each to make a separate request for the function. The consultation tests that model against voluntary devolution and other options. It does not transfer any legal powers immediately: decisions remain subject to the existing regime while ministers consider the responses and determine how to implement any reform. This distinction is relevant to current promoters preparing applications under the rules already in force.
Responsibility would extend beyond signing the final order. Mayoral authorities would manage the application, assess and handle objections, oversee any inquiry process and issue the decision. The department has considered retaining central management of applications while transferring only the final decision, but its consultation argues that split responsibility might add administrative handovers and restrict opportunities to improve the process. The proposed end-to-end model would place both procedural management and determination within the same organisation for eligible schemes.
National rail infrastructure is a specific exclusion. Rail capacity, train paths and engineering possessions can cross regional boundaries even when a physical scheme is situated within a single mayoral area. The consultation consequently proposes that applications relating to the national rail network remain with the relevant central decision maker. A tram or guided bus scheme wholly inside one authority could follow a different route, provided the final legislation reflects the proposal. Projects spanning multiple mayoral areas would also initially remain centrally handled.
A promoter submitting an eligible scheme would deal with the mayoral strategic authority as the body administering and determining the application if the proposal were enacted. The statutory application requirements, environmental assessment, public consultation and objection mechanisms would still apply. A local decision maker could bring administrative responsibility closer to the proposed route, but the department has not established that transferring functions would shorten a particular project’s approval timetable. The extent of procedural change will depend on the final legal framework and the resources available to each authority.
The legal character of these decisions remains demanding. Transport and Works Act determinations are quasi-judicial and require a decision on the evidence before the authority, without bias or conflicts of interest. Some mayoral bodies could also be sponsors, funders or strategic promoters of the schemes they are asked to determine. The government is seeking views on governance arrangements to manage actual or perceived conflicts where the same authority has these different roles.
Transport and Works Act orders can modify existing legislation, while decisions may involve deemed planning permission and related statutory consents. The consultation therefore examines the legal form in which an order would be made if a mayoral authority decided the application. Options include giving authorities limited powers to make locally applicable statutory instruments or retaining a central role in issuing the instrument after the local decision. The choice affects how the resulting powers are documented and enforced, not whether applicants may dispense with environmental or planning requirements.
Legal challenge is another area under review. The government proposes that a mayoral authority should meet costs arising from challenges to decisions it has taken, including potential costs incurred by central government where it is involved in the proceedings. It is consulting on safeguards and whether authorities should be able to refer individual applications back to ministers. Any referral mechanism would need to be defined carefully to avoid creating uncertainty over who ultimately owns the decision.
The specialist workload is relatively small. The department reports an average of around five Transport and Works Act applications each year over the previous decade, with slightly more than half relating to the national rail network. Once those national cases are excluded, individual mayoral authorities could receive applications only intermittently. The department is therefore testing whether legal drafting, transport planning and environmental assessment expertise could be maintained locally, and whether central government or the Planning Inspectorate should provide training, workshops or temporary assistance on a cost recovery basis.
Application fees are also under consideration. Existing fees are prescribed nationally, and the government is asking whether one fee structure should continue or whether mayoral authorities could set their own fees subject to cost recovery principles. A common structure could help promoters budget consistently, while locally set fees might reflect differences in administrative costs. The consultation does not establish a new fee rate or identify specific projects that would switch decision maker immediately.
The department is inviting evidence from infrastructure promoters, mayoral and local authorities, statutory consultees and other affected organisations. Responses must arrive by 11.59pm on 18 December 2026. The government will then decide whether and how to proceed, including the allocation of legal costs, the structure of application fees and the mechanism for resolving potential conflicts where an authority also sponsors a scheme. Existing Transport and Works Act approval arrangements continue in the meantime.