IN Brief:
- Bouygues UK can continue its challenge to the Department for Education's £15.4bn Construction Framework 25 procurement.
- The High Court held that a statutory filing deadline falling on a Saturday extended to the following working day.
- The judgment resolves preliminary limitation questions without determining whether the original bid evaluation was unlawful.
Bouygues UK can continue its legal challenge to a Department for Education construction framework after the High Court rejected the government’s argument that proceedings were commenced outside the statutory deadline. The Technology and Construction Court ruled on 19 November that the contractor’s claim was brought in time, allowing its challenge to the procurement evaluation to proceed.
The dispute concerns Construction Framework 25, a procurement with an estimated value of £15.4bn covering construction projects for educational buildings. Bouygues competed for Lot 2, which was structured to appoint ten suppliers. The contractor finished eleventh, narrowly missing a framework place.
Bouygues received an evaluation score of 74.67, compared with 74.8 for the tenth-ranked bidder, McLaren Construction. The difference of 0.13 points forms part of the underlying dispute, with Bouygues alleging errors in the evaluation of its tender and unfair treatment in comparison with the successful competitor.
Those allegations have not yet been determined by the court. The latest judgment addresses preliminary issues concerning the time limit for bringing the claim, the effect of a deadline falling on a day when the court office was closed, and the legal treatment of documents submitted through the electronic filing system.
The Department for Education provided Bouygues with its assessment summary at 10:59 on Friday 5 December 2025. Section 106 of the Procurement Act 2023 generally requires proceedings to begin within 30 days of the date on which the supplier first knew, or ought to have known, of the circumstances giving rise to its claim.
Bouygues argued that the limitation period should begin later, after the company had considered the evaluation material and obtained advice. Mr Justice Coppel rejected that interpretation for the original scoring challenge, finding that the relevant information had already been available when the assessment summary was received.
The judge distinguished knowledge of the underlying facts from a supplier’s subsequent assessment of their legal significance. A company does not ordinarily gain additional time merely because it takes several days to analyse an evaluation or decide whether to pursue litigation. On the facts of the case, the statutory period began on 5 December 2025.
Counting the 30-day period from that date placed the final day on Saturday 3 January 2026. The department argued that the contractor should have submitted its claim by that date, particularly because the court’s CE-File system permits electronic submissions outside normal working hours.
The High Court rejected that argument. Applying the established common law principle governing deadlines that expire when the relevant court office is closed, the judge held that the period extended to the next working day, Monday 5 January 2026.
Electronic filing did not remove the distinction between submitting documents and the court office being open to process them. Although CE-File can receive material over a weekend, the administrative processes associated with accepting and issuing a claim remain subject to the applicable procedural rules.
Bouygues submitted its claim form electronically on 5 January and paid the required fee that day. The court formally issued the document on 7 January, recording 5 January as its issue date. The judge concluded that the proceedings were commenced on the earlier date under the applicable electronic filing rules.
The claim was therefore brought within the statutory period as extended to the first working day after the weekend. The court also considered the alternative position that would have applied had it found the proceedings to be late. In those circumstances, Mr Justice Coppel indicated that an extension would have been granted under section 106(3).
The proposed extension was assessed against the circumstances of the short delay, the novelty of the legal issue, and the practical effect on the parties. The Christmas and New Year period had affected the time available to investigate the evaluation, while the court found that the delay had not caused material prejudice sufficient to justify refusing an extension.
Further issues concerned allegations arising from later information about the procurement’s evaluation and moderation procedures. The court distinguished material providing additional evidence for the original scoring challenge from allegations concerning separate record-keeping and disclosure obligations. The latter could involve different dates of knowledge and separate limitation questions.
The distinction reflects the way procurement claims can develop as documents become available. An unsuccessful bidder may initially know the scores and reasons provided in an assessment summary, while subsequent disclosure reveals further information about the evaluation process. Whether that information supports an existing allegation or establishes a different alleged breach can affect the applicable limitation analysis.
The judgment does not establish that Bouygues should have been appointed to the framework. Nor does it find that the Department for Education breached its procurement obligations or that McLaren’s evaluation was improper. Those questions remain part of the substantive dispute.
The relevant framework agreements have already been concluded with successful bidders. That affects the potential remedies available if Bouygues ultimately establishes an unlawful procurement decision, because the challenge is proceeding after contract conclusion rather than during a period when the award could be suspended pending the outcome.
Construction frameworks are used to establish procurement arrangements through which public authorities can appoint contractors for future projects. An unsuccessful supplier may lose access to a substantial pipeline of potential opportunities, although appointment to a framework does not itself guarantee a particular volume of construction work.
The narrow scoring difference in the Bouygues dispute illustrates how a small change in an evaluation outcome can determine whether a supplier qualifies for a limited number of framework places. The legal questions surrounding the evaluation remain separate from the preliminary issue of whether the contractor acted within the permitted filing period.
The decision also establishes an important interpretation of the Procurement Act 2023’s limitation rules. Receiving an assessment summary can start the statutory clock, even where detailed legal analysis follows later, but a deadline ending when the court office is closed may extend to the next working day.
With those preliminary issues resolved, the proceedings can continue towards consideration of the procurement allegations themselves. The ultimate outcome will depend on whether Bouygues can establish the alleged evaluation breaches and, if so, what remedy is available following the conclusion of the framework agreements.



