McPhillips completes A457 Dudley Road improvements

McPhillips completes A457 Dudley Road improvements

McPhillips has completed Birmingham’s four-phase Dudley Road transport improvement scheme. Construction incorporated segregated cycling infrastructure, redesigned junctions, utility protection measures, and a new pedestrian and cycle bridge across the Soho Loop Canal.


IN Brief:

  • Birmingham City Council confirmed completion of the four-phase A457 improvement programme on 23 November.
  • The final construction phase connected previously completed sections of segregated cycling infrastructure.
  • Vacuum excavation and structural monitoring supported construction around existing utilities, bridges, and operational healthcare facilities.

Civil engineering contractor McPhillips has completed the four-phase improvement of Birmingham’s A457 Dudley Road corridor, delivering segregated cycling infrastructure, bus lanes, redesigned junctions, and pedestrian facilities along a principal transport route between Birmingham and Sandwell.

Birmingham City Council confirmed completion of the programme on 23 November following the conclusion of construction in October. The final phase established a continuous segregated cycling route between Aberdeen Street and Western Road, connecting sections of infrastructure delivered during earlier stages.

The wider scheme received £19.94m through the government’s Levelling Up Fund, supporting a construction programme that began in 2021. The funding contribution represents part of the investment in the corridor rather than a confirmed final construction cost for the entire programme.

The first phase, completed in May 2022, improved capacity and pedestrian infrastructure at the Western Road junction while supporting access to the Soho Loop regeneration area, where approximately 3,000 new homes are anticipated.

Construction subsequently progressed across Spring Hill, the Barford Estate, and the Heath Street and Winson Green Road sections. Completed in August 2024, the second phase introduced tidal flow bus lanes, bus lane enforcement infrastructure, upgraded crossings, and a new shared pedestrian and cycle bridge alongside the existing canal crossing.

The aluminium bridge was manufactured in Germany before transportation to Birmingham. McPhillips appointed a specialist installation contractor to coordinate technical requirements with the manufacturer, establishing the arrangements necessary to install the prefabricated structure within the constraints of the existing highway and canal infrastructure.

Manufacturing the bridge away from the construction site allowed fabrication to progress independently of the highway works. Installation nevertheless depended on the readiness of supporting structures, the availability of appropriate lifting equipment, and coordination with road and canal operators.

The third phase, completed in April 2026, addressed Lee Bridge and the Icknield Port Road junction. Construction included changes to carriageway and footway alignments, with continuous structural and vibration monitoring undertaken at Lee Bridge.

Monitoring allows construction teams to assess the response of existing structures to activities taking place nearby. Excavation, compaction, and changes to temporary loading conditions can influence structural movement, while construction machinery can introduce vibration that must remain within limits appropriate to the condition of retained infrastructure.

The monitoring requirements depend on the characteristics of the structure, the proposed construction methodology, and the potential consequences of movement. McPhillips has not disclosed the individual instruments, monitoring thresholds, or measurements recorded during the Lee Bridge works.

The final phase extended the segregated cycling infrastructure across the frontage of the former City Hospital and Birmingham Treatment Centre. Changes to parking and access arrangements were incorporated alongside the new cycle track.

Construction throughout the wider Dudley Road scheme encountered extensive existing utility infrastructure, including services associated with a major electricity substation. McPhillips introduced vacuum excavation to address restrictions on conventional mechanical excavation around those assets.

Vacuum excavation removes loosened ground material through a suction system connected to a collection chamber. When appropriately applied, the technique can expose buried infrastructure without requiring an excavator bucket to operate immediately alongside cables, pipes, and their connections.

The resulting improvement in excavation control can reduce the risk of damage to buried services, particularly where existing utility records provide incomplete information about their location. Service identification, appropriate excavation procedures, and compliance with safe working requirements remain necessary.

McPhillips reports that using vacuum excavation accelerated progress during the scheme. Its suitability for individual excavation activities would have depended on ground conditions, the accessibility of buried infrastructure, and the volume of material requiring removal.

Maintaining access to operational healthcare facilities introduced further constraints. The corridor serves several medical facilities, including the Midland Metropolitan University Hospital in Smethwick, which opened in October 2024.

Night and weekend construction supported the delivery of activities that could not readily be accommodated within normal traffic arrangements. Managing those working periods required coordination between construction activities, public transport operations, and access for healthcare workers and patients.

The completed cycling route also required integration with the existing drainage, carriageway, and pedestrian infrastructure. Reallocating highway space can alter the position of kerbs, drainage channels, crossings, and traffic signal equipment, requiring coordinated design rather than an isolated change to road markings.

Completing the four phases separately allowed individual sections to enter use while construction continued elsewhere. The October works established the remaining link between the previously delivered cycling routes, completing the continuous corridor.

Birmingham City Council expects the improvements to support safer journeys, more reliable public transport, and access to existing and emerging development areas. With construction complete, operational performance will determine the extent to which the revised highway arrangements achieve those objectives.



  • Government directs Rochford to reinstate housing allocations

    Government directs Rochford to reinstate housing allocations

    Rochford must consult on six previously removed strategic housing allocations. Government intervention requires the Essex authority to begin its final Local Plan consultation on 7 December, with submission for independent examination required by 31 March 2027.


  • Public construction contract notices total £98.5m

    Public construction contract notices total £98.5m

    Public construction contract notices totalled £98.5m during November’s third week. Scottish housing and civil engineering projects accounted for more than half of the recorded value, including CCG’s £49m West Lothian Council housing appointment.