IN Brief:
- The 5,030m² school is being constructed alongside the existing Thomas Clarkson Academy.
- Photovoltaic generation will be integrated into a vegetated roof and external canopies.
- The Department for Education framework project is expected to provide permanent accommodation during 2028.
Henry Brothers has outlined construction specifications for the £24m permanent home of The Wisbech Academy in Cambridgeshire, where a structural steel building incorporating piled foundations and a bio-solar roof will provide capacity for 600 secondary school pupils.
The 5,030m² development is being constructed alongside Thomas Clarkson Academy, with accommodation for 120 pupils in each of the five year groups between Years 7 and 11. Both schools operate under the Brooke Weston Trust.
Henry Brothers is delivering the project through the Department for Education Construction Framework, with CPMG, Hexa, and Anderson Green providing design consultancy services. Construction is expected to provide permanent accommodation during 2028.
The Wisbech Academy began operating in September 2024, initially using facilities at Thomas Clarkson Academy before moving into temporary accommodation. Planning approval for its permanent building followed in July 2025, with initial construction activities confirmed by the trust in September 2026.
The latest construction specifications identify a three-storey building incorporating piled foundations, a steel frame, and a brickwork façade. External works include sports provision, access infrastructure, landscaping, and photovoltaic installations across several canopies.
Piled foundations provide a means of transferring structural loads into the supporting ground through relatively slender foundation elements extending beneath the building. Depending on their design, piles develop resistance through friction or adhesion along their shafts, bearing resistance at their bases, or a combination of both mechanisms.
Selection of the foundation system depends on the ground conditions identified through site investigations, anticipated structural loads, and the settlement that can be accommodated by the building. The piling methodology, dimensions, and founding depths selected for Wisbech have not been disclosed.
The steel frame will establish the primary supporting structure for the building’s floors and roof, with its configuration influenced by the layout of teaching spaces, circulation routes, and other educational facilities.
Different areas of a school impose varying requirements on the structural design. Conventional classrooms can generally be accommodated within relatively regular structural grids, while larger communal or specialist teaching spaces may require wider spans and different service distribution arrangements.
Coordinating these requirements during design helps establish the locations of structural supports and openings before individual steel members are manufactured. Subsequent mechanical and electrical installations must remain compatible with the resulting geometry and the fire protection applied to structural elements.
The brickwork façade introduces additional interfaces between the external walls and the supporting frame. Connections must accommodate the weight of the masonry alongside differential movement between construction materials, while cavity arrangements and weatherproofing details maintain the performance of the external envelope.
Renewable electricity generation will form part of the roof construction through a bio-solar system combining photovoltaic modules with vegetation. Separate photovoltaic arrays across external canopies will increase the area available for electricity generation beyond the main building footprint.
Combining vegetated roofing with solar generation allows both systems to occupy overlapping areas of the roof. Photovoltaic modules are typically mounted above the growing medium, allowing vegetation to establish beneath and around the supporting structures.
Evapotranspiration from vegetation can influence the temperature of the surrounding roof environment. Because photovoltaic module efficiency generally declines as operating temperature increases, that cooling effect can potentially support electricity generation, although the outcome depends on vegetation characteristics, module clearance, system configuration, and weather conditions.
The combined arrangement introduces additional requirements for structural loading and drainage. Growing media retain water, increasing their mass during wet conditions, while photovoltaic modules and their supporting equipment impose permanent loads that must be accommodated by the roof structure.
Waterproofing and drainage must also remain accessible for inspection and maintenance. The positioning of photovoltaic supports, electrical cables, and vegetation must allow water to reach drainage outlets without creating obstructions or compromising the underlying roof membrane.
External canopy installations present a different set of structural requirements. Their supports must accommodate the weight of the photovoltaic equipment and wind loading while maintaining clearances appropriate to the pedestrian or other activities taking place beneath them.
The installed photovoltaic capacity and projected annual electricity generation at Wisbech have not been disclosed. Those figures will depend on the available installation areas and equipment specifications, while the extent to which the school can directly use generated electricity will reflect its operational demand and the timing of generation.
Construction alongside an existing secondary school requires coordination of deliveries, plant movements, and access arrangements with educational activities. Work affecting shared access infrastructure or existing utility connections may also need to be phased around the continued operation of neighbouring facilities.
The current construction programme will progress through foundation installation, structural erection, building enclosure, services installation, and internal fit-out before testing and commissioning the permanent accommodation. Completion during 2028 will allow The Wisbech Academy to transfer its operations from temporary facilities into a building designed around its full five-year-group capacity.