Protos ERF reaches first-fire milestone

Protos ERF reaches first-fire milestone

Protos ERF has reached first fire during hot commissioning works. The Cheshire energy-recovery facility is nearing operation while construction progresses on an adjoining full-scale carbon-capture plant due online in 2029.


IN Brief:

  • First fire moves the 500,000-tonne-a-year Protos ERF into the final stages of hot commissioning.
  • The facility is designed to generate up to 49.9MW of baseload electricity while recovering aggregate and metals from residual waste.
  • An adjoining carbon-capture plant is under construction and is expected to capture around 370,000 tonnes of carbon dioxide annually from 2029.

First fire on waste at the Protos Energy Recovery Facility in Cheshire has moved the project into the closing stages of hot commissioning while construction continues on a full-scale carbon-capture plant immediately alongside it.

METLEN confirmed the first-fire milestone on 21 August at the facility it is developing for Encyclis near Ellesmere Port. Protos is designed to process up to 500,000 tonnes of non-recyclable residual waste each year and generate as much as 49.9MW of baseload electricity.

First fire is a significant commissioning step because it moves the plant from progressive equipment testing into operation with the material it was designed to process. Fuel handling, combustion systems, boiler plant, flue-gas treatment, controls, electrical equipment, and supporting utilities must operate together under live conditions rather than through isolated cold tests.

Hot commissioning began earlier this year, with engineers progressively bringing mechanical and electrical systems online before waste deliveries and first fire. Encyclis had also recruited more than 40 operations and maintenance staff ahead of the transition, reflecting the point at which responsibility begins to shift from construction teams towards the permanent operating organisation.

That handover is necessarily gradual on a process plant. Combustion stability, emissions performance, control sequences, safety systems, plant availability, and electrical export all have to be demonstrated before the facility can settle into routine commercial operation.

Once fully operational, Protos will treat residual household and commercial waste remaining after recycling. The combustion process will produce electricity, while bottom ash can be processed into secondary aggregate and ferrous and non-ferrous metals recovered for reuse.

The commissioning work is taking place beside another major construction programme. Encyclis is building a full-scale carbon-capture facility on adjoining land as part of the HyNet North West industrial decarbonisation cluster, creating an unusual overlap between the final stages of one project and the heavy construction phase of the next.

Site establishment for the carbon-capture plant has been completed and piling activity is under way. Kanadevia Inova is working on the project, which is expected to become operational in 2029 and capture around 370,000 tonnes of carbon dioxide a year from the energy-recovery process.

The captured gas is intended to enter the HyNet transport network before permanent geological storage beneath Liverpool Bay. That means the carbon-capture facility has to integrate not only with the existing ERF but also with off-site pipeline and storage infrastructure being developed as part of the wider cluster.

For construction teams, carbon capture adds a substantial process-engineering project rather than a bolt-on emissions device. Flue-gas connections, cooling, absorption equipment, regeneration systems, compression, pipework, electrical systems, instrumentation, access structures, foundations, utilities, and control interfaces all have to be incorporated without compromising operation of the host facility.

The sequencing challenge will become more demanding once the ERF is fully operational. Construction activity beside a working waste-processing plant must be managed around live process equipment, vehicle movements, operational safety systems, maintenance access, and planned shutdown periods required for final integration.

That makes Protos useful as an early example of what large-scale carbon-capture deployment could mean for the construction sector. The technology is frequently discussed in terms of tonnes of carbon avoided, but delivering it requires conventional civil, structural, mechanical, electrical, and process disciplines at significant scale.

Encyclis expects construction and commissioning of the carbon-capture project to support up to 500 skilled jobs, extending specialist engineering demand on the site after the energy-recovery facility itself moves beyond peak construction.

The two projects also operate on different timescales. First fire does not mean the ERF has completed every commissioning test, and the carbon-capture system will not begin operating alongside it immediately. The waste plant is approaching routine service now, while the adjoining capture facility has a programme extending to 2029.

That gap will require the original plant to operate in a form that can later be integrated with the new process. Interface management, future shutdown planning, space allocation, duct routes, steam and power requirements, and control-system changes will all have to be accounted for while the ERF is already performing its primary waste-treatment role.

Protos is therefore not reaching the end of construction so much as changing phases. The first fire confirms that the core energy-recovery plant is approaching operation, but piling and other works on the adjoining carbon-capture project ensure the site will remain an active engineering programme for several more years.



  • Ipswich secures site and designs for Broomhill Lido restoration

    Ipswich secures site and designs for Broomhill Lido restoration

    Ipswich Borough Council has secured control of historic Broomhill Lido. The council has obtained possession of the Grade II-listed complex and rights to existing redevelopment designs, allowing specialist appointments, funding applications and construction procurement preparations to advance.


  • Willmott Dixon completes £15.6m Manchester bus depot upgrades

    Willmott Dixon completes £15.6m Manchester bus depot upgrades

    Willmott Dixon has completed electrification works at two Manchester depots. The £15.6m programme at Hyde Road and Oldham delivered 138 electric vehicle chargers, a private high-voltage substation and associated distribution infrastructure while both facilities remained operational.