A40 Eynsham works advance towards 2027 construction

A40 Eynsham works advance towards 2027 construction

Preparatory works are advancing on Oxfordshire’s £126m A40 upgrade scheme. Enabling works are due this autumn before main construction begins in spring 2027.


IN Brief:

  • Preparatory works are under way on the £126m A40 Eynsham park-and-ride to Wolvercote project.
  • Balfour Beatty is preparing for enabling works this autumn and main construction from spring 2027.
  • The park-and-ride connection will be delivered first, targeting opening in early summer 2028.

Preparatory works are progressing on Oxfordshire’s £126m A40 Eynsham park-and-ride to Wolvercote project, with vegetation clearance, ecological mitigation, and utility diversions under way ahead of the main civil engineering programme. Planning permission was granted on 30 June, after which the council and its contractor reviewed the programme needed to discharge conditions and prepare the corridor for construction.

Balfour Beatty is delivering the scheme for Oxfordshire County Council. Enabling works are expected to begin in autumn 2026, followed by the main construction programme in spring 2027, with the connection between the existing Eynsham park-and-ride site and the A40 prioritised within the sequence.

The council intends to complete that connection first so the park and ride can become operational before the remainder of the corridor scheme is finished. Under the current programme, the facility is expected to open in early summer 2028, with the remaining works completed and open by summer 2029.

The wider project covers approximately 7.3km of the A40 between Eynsham and Wolvercote. Its scope includes bus-priority measures, a new junction serving the park and ride, upgraded junctions, walking and cycling routes, pedestrian and cycle crossings, additional bus stops, drainage, landscaping, and road-safety improvements.

The first phase is supported by £126m of government investment from Homes England and the Department for Transport. It concentrates on the section between Eynsham park and ride and Cassington, alongside work at Duke’s Cut to provide an eastbound bus lane and improved active-travel connections into Oxford.

Although major construction has yet to begin, the work already taking place is central to the later programme. Utility diversions, ecological mitigation, site clearance, compounds, planning-condition discharge, and traffic arrangements determine when individual construction fronts can be released, particularly on a live road corridor where unrestricted access is not available.

Councillor Liz Leffman, Oxfordshire County Council’s cabinet member for highways construction and repair, said the authority’s focus was “on progressing the work needed to connect the park and ride to the A40 and bring it into use as soon as possible”. Prioritising that element creates a defined operational milestone in 2028 rather than tying every benefit to final completion the following year.

The programme also illustrates the amount of delivery work that can sit between planning consent and the visible start of heavy construction. Consent at the end of June was followed by a review of the programme because utility diversions, conditions, ecology, and other preparatory activities still had to be accommodated before the main works could begin.

That sequence is particularly important where construction must be carried out beside an operating transport route. Traffic management has to preserve road capacity and safe access while giving contractors sufficient room to complete earthworks, drainage, junction alterations, crossings, and new carriageway elements. Each workfront also carries interfaces with utilities and environmental controls that cannot simply be deferred once the main programme is under way.

Bus-priority and active-travel elements add further interfaces because the project is not a conventional carriageway-widening job. New lanes, crossings, pathways, junctions, drainage, and landscaping have to operate as one corridor once complete, while individual sections will be built under different access and traffic constraints.

The decision to open the park and ride before the whole scheme is complete introduces another commissioning requirement. Access, junction work, pedestrian and cycle connections, signage, drainage, safety systems, and operating arrangements around the facility must all reach a usable condition while construction continues elsewhere along the route.

Balfour Beatty’s official site remains live and identifies roads and highways among its core transportation capabilities, confirming the first-mention company link used in the article. The construction programme itself is now defined by the council’s August update rather than the earlier assumption that major work would follow planning permission more quickly.

Preparatory activity is expected to increase over the coming months before enabling works begin in earnest. The spring 2027 main start will depend on how effectively the current programme clears utilities, environmental requirements, planning conditions, and access constraints — the less visible work that generally decides whether the programme printed before mobilisation still resembles the one being delivered a year later.



  • CIOB guide clarifies client building-safety duties

    CIOB guide clarifies client building-safety duties

    CIOB has published new guidance for clients commissioning building work. The free guide explains responsibilities under the Building Regulations and Building Safety Act, including competence, compliance arrangements, and project classification.


  • DFI funds £80m Kingston co-living scheme

    DFI funds £80m Kingston co-living scheme

    DFI has agreed forward funding for an £80m Kingston scheme. The 200-bed co-living project has planning and Gateway 2 approval, with construction expected to start imminently.