Watkin Jones appointed to Manchester student scheme

Watkin Jones appointed to Manchester student scheme

Watkin Jones will deliver Jadebricks’ Manchester student accommodation tower scheme. Enabling works are planned before October ends, with 107 studios scheduled for completion ahead of the 2028–29 academic year.


IN Brief:

  • Watkin Jones is the delivery partner for Jadebricks’ 15-storey Charles Street purpose-built student accommodation project in Manchester.
  • The design by SimpsonHaugh includes 107 studio rooms on a former city-centre car park, with BREEAM Excellent targeted in the planning proposal.
  • Enabling works are expected in October 2026 and completion is targeted for the 2028–29 academic year, subject to construction progress.

Watkin Jones has been appointed to construct Jadebricks’ 15-storey student accommodation scheme on Charles Street in central Manchester, with enabling works expected before the end of October 2026. The project comprises 107 studio rooms on a former car park between the Maldron Hotel and Bracken House. The developer is targeting completion ahead of the 2028–29 academic year. The appointment establishes a delivery partner and an intended timetable, but the October start remains prospective until site works are confirmed.

The compact city centre site sits within the Oxford Road Corridor, near Manchester’s university campuses. SimpsonHaugh designed the building, and Turley led planning work on behalf of Jadebricks. A planning application was submitted in December 2023 and obtained committee approval in May 2024; the contractor agreement is consequently a delivery development on an already consented project rather than a new planning application. The earlier design material specified 107 studios over 15 storeys, while some subsequent summaries rounded that figure to approximately 100 rooms.

Jadebricks and Watkin Jones are working together on this project for the first time. Watkin Jones has described the appointment as a return to Manchester and an addition to its student accommodation construction pipeline. Neither the contract value nor the procurement terms have been disclosed, so the agreement should not be assigned a speculative build cost or a particular commercial risk structure. A date for enabling works has been reported, but no separate statement confirms that piling, excavations, or other main construction activities have commenced.

A former car park between existing buildings offers limited room for materials handling and temporary construction facilities. During detailed mobilisation, the delivery team will need to resolve deliveries, lifting and access arrangements within the permitted street and site constraints, and protect neighbouring premises from avoidable disruption. The project information does not specify a tower crane, foundation approach, prefabricated module system, or facade installation method. Those choices cannot responsibly be inferred from the building’s height or from techniques the contractor has used elsewhere.

The planning proposal targeted BREEAM Excellent, which assesses a range of environmental performance categories including energy, materials, water, transport, and management. The target depends on the design being carried through procurement, construction, and assessment; it is not an award already secured for the finished building. Sustainability performance at Charles Street therefore remains a commitment to be demonstrated through specification and recorded outcomes. The project team has not published a final BREEAM certificate or independently verified post-occupation energy figures.

The student accommodation is intended to bring a residential use to an underused gap in the established city-centre streetscape. Turley’s planning material described the proposal as completing the street frontage and increasing activity along Charles Street. That objective has to be balanced against the needs of the adjoining hotel, nearby premises, pedestrians, and local traffic during construction. Detailed controls relating to hours, vehicle movements, noise, and the public highway should follow applicable permissions and management plans; the latest contractor appointment does not itself disclose those arrangements.

The reported completion programme is tied to the 2028–29 academic year, making the timing of handover relevant to the building’s intended use. The development is purpose-built student accommodation rather than a conventional block of apartments, and the 107 studios will need to be commissioned and accepted before residents can occupy them. The contractor has not announced a practical completion date, and the academic-year target is not equivalent to confirmed availability for that intake. Any change to site conditions or approved design could affect that timetable.

The 2023 planning material named a broad consultant team covering engineering, environmental assessment, heritage, acoustics, and fire. Those planning roles are evidence of the earlier design process, not proof of appointments to the construction supply chain in October 2026. The revised delivery programme will require the contractor and developer to coordinate building regulations compliance, logistics, and neighbouring operations, but there is no published information identifying final trade contractors or construction-stage technical packages.

The first reliable next step will be confirmation that enabling works have begun on Charles Street, followed by clearer information about the main construction programme. Watkin Jones is appointed to deliver the building and Jadebricks has an intended academic-year deadline; neither fact establishes that the tower is under construction or that environmental certification has been achieved. The project moves into delivery planning with 107 studios and the consented 15-storey scheme as its reported scope.



  • Cross-pavement EV charging gains planning exemption

    Cross-pavement EV charging gains planning exemption

    England has introduced new rights for cross-pavement vehicle charging installations. Qualifying pavement cable channels no longer require an individual planning application, but highway authority authorisation and restrictions on protected locations continue to apply.


  • Watkin Jones appointed to Manchester student scheme

    Watkin Jones appointed to Manchester student scheme

    Watkin Jones will deliver Jadebricks’ Manchester student accommodation tower scheme. Enabling works are planned before October ends, with 107 studios scheduled for completion ahead of the 2028–29 academic year.