IN Brief:
- Capital funding for the first four years of RIS3 will fall by £428m, including £315m in enhancements expenditure associated with the two schemes.
- Both projects had obtained development consent before the government confirmed their cancellation.
- The East Midlands mayor has proposed a regional investment of up to £100m towards developing local solutions.
The Department for Transport has cancelled the A38 Derby Junctions and A46 Newark Bypass projects, removing two consented civil engineering schemes from the third Road Investment Strategy (RIS3). The decision reduces planned capital funding for England’s strategic road network by £428m over the first four years of the investment period.
The variation to RIS3, published on 26 November, reduces enhancements funding by £315m across the financial years 2026–27 to 2029–30. A further £113m reduction applies to other capital expenditure. The £315m represents expenditure removed from the investment programme during those years, rather than the combined lifetime cost of building both schemes.
The decision follows a consultation launched in July and concluded on 14 September. The Department for Transport assessed responses and evidence concerning safety, housing, economic growth, the environment, affordability, and deliverability before determining that the schemes could no longer be accommodated within the revised programme. The changes follow an earlier decision to redirect expenditure towards national security and defence.
Both projects had obtained development consent before cancellation. The A38 Derby Junctions development consent order was approved in August 2023 following redetermination by the transport secretary. Approval of the A46 Newark Bypass order followed on 1 October 2025. The two schemes were included in RIS3 when the strategy was published in March 2026.
The Derby project covered three major intersections at Kingsway, Markeaton, and Little Eaton, where traffic on the A38 currently interacts with vehicles joining or leaving the route. The scheme would have separated through traffic from local junction movements, reducing the need for strategic traffic to negotiate the existing roundabouts.
The planned works would have required major alterations to the existing highway corridor, including structural engineering, earthworks, and changes to connections with the local network. Grade separation involves creating distinct levels for traffic movements, with the associated geometry often requiring retaining structures, new bridge structures, and approaches constructed around the existing highway.
National Highways had continued preparations for the Derby project following the conclusion of a legal challenge, including localised site surveys during 2025 and early 2026. Such investigations inform detailed design by establishing conditions that may affect foundation requirements, underground services, and the construction arrangements needed within an operational road corridor.
At Newark, the proposed works included converting approximately 6.5km of existing single carriageway into dual carriageway between Farndon and Winthorpe. The section forms part of a strategic route connecting the Midlands to Lincolnshire and the Humber. Its interfaces with the A1 and surrounding local network were central to the scheme’s wider transport function.
Skanska had been involved in the Newark scheme’s design and statutory planning stages. Its earlier agreement ended in June 2026, before the decision on the variation to RIS3. The government confirmed in July that the contractor had contributed to the progression of the project through development consent. The latest decision therefore removes prospective main construction work, rather than stopping an active principal works contract.
The projects would have generated demand for a combination of structural design, ground engineering, earthmoving, pavement construction, drainage, and temporary traffic management. Removing both schemes from the current programme changes the opportunities available to contractors and specialist subcontractors planning future workloads in the East Midlands.
The Chartered Institution of Highways and Transportation has expressed concern over the confirmed reductions. The East Midlands Combined County Authority has also responded to the decision, with mayor Claire Ward proposing that the region invest up to £100m of its resources in developing and delivering local solutions for the two routes. That proposal is distinct from reinstatement of the cancelled National Highways schemes; the engineering scope and funding arrangements of any alternatives have yet to be established.
Future proposals will need to account for the existing network’s constraints alongside the affordability and feasibility of different interventions. Smaller junction or operational improvements may have a different construction scope from the previously consented projects, and would require their own assessment against the issues identified along the routes.
RIS3 remains the framework for National Highways’ investment and operation of the strategic road network until March 2031. The existing Derby and Newark roads will remain operational, with any future enhancement proposals dependent on separate investment decisions. The cancellation leaves two developed and consented projects outside the current delivery programme, while regional authorities consider whether alternative works can be brought forward.



