A54 Cat and Fiddle road reopens after £3m upgrade

A54 Cat and Fiddle road reopens after £3m upgrade

Derbyshire has reopened the A54 following major road reconstruction works. The first phase finished almost three weeks ahead of schedule, while further drainage and embankment stabilisation remain programmed for spring 2027.


IN Brief:

  • The first phase covered a 1.7km section of the A54 and included full-depth road reconstruction, surfacing and drainage improvements.
  • Approximately 250 metres of new drainage pipe were installed before the road reopened on 12 October.
  • Further earth-bank strengthening and culvert works are scheduled for an approximately 11-week closure in spring 2027.

Derbyshire County Council has reopened the A54 Macclesfield Main Road, known as the Cat and Fiddle, almost three weeks before its planned 30 October reopening after completing the first phase of a £3m reconstruction and road safety programme. The route between the A53 Leek Road junction and the A537 at the county boundary returned to traffic on 12 October. The first phase covered 1.7km of a wider programme described by the council as extending over 2.8km.

The road had been fully closed since 27 July to allow excavation across its width, reconstruction of damaged sections, drainage installation and resurfacing. The council attributed the earlier reopening to site planning, favourable weather and progress by teams working during daytime and overnight shifts. The route connects communities and commercial traffic moving between Derbyshire, Cheshire and Staffordshire, making the duration of the closure an important part of the project programme.

Much of the first phase involved work below the finished carriageway rather than surface treatment alone. Sections of the road were rebuilt with new foundations before resurfacing, while high-friction treatment was applied to improve skid resistance. The council also installed new road markings and reflective studs, replaced or repaired traffic signs, and added kerbs and reflective bollards. These elements address different road safety conditions, particularly where changing weather affects the visibility and grip available to drivers.

Approximately 250 metres of new drainage pipe were installed alongside improvements to gullies, chambers, connections and outfalls. Removing surface water helps maintain tyre grip, but the drainage also protects the reconstructed pavement layers: moisture that enters the road structure can contribute to loss of support and freeze-thaw damage. On this exposed upland route, the ability to drain rainfall and runoff away from the carriageway is a central part of its winter resilience rather than an incidental finishing task.

Because excavations occupied the full width of the road, keeping a traffic lane open alongside the works was not considered practicable. The complete closure also allowed several activities to be brought together within one possession of the highway, rather than returning for successive surface and drainage interventions. This sequencing did not remove the disruption to local journeys, but it avoided having to implement a separate closure for each element of the first-phase scope.

Traffic was directed along an official diversion using the A54, A523 and A53. Derbyshire selected that route as a suitable alternative for all classes of vehicle, including buses and heavy goods vehicles, rather than directing larger traffic onto minor roads. Until the reopening, the diversion formed part of the traffic management arrangements for a programme that had originally been scheduled to run for 14 weeks.

Funded by the East Midlands Combined County Authority and delivered by Derbyshire County Council, the programme is intended to reduce repeat maintenance interventions on a route affected by wet weather, frost and constrained working space. The authority confirms that the first stage is complete, although the reopening cannot yet be treated as practical completion of the whole £3m scheme. It has deliberately separated the pre-winter road and drainage package from work on adjoining slopes planned for the following spring.

A second construction phase is planned for spring 2027, when approximately 11 weeks of further activity are expected. That package will concentrate partly on the earth banks adjoining the road. Strengthening and repairing those banks is intended to reduce the risk of soil and rock falling onto the carriageway during adverse weather. The council also plans visibility improvements and the completion of remaining resurfacing, drainage and culvert installation, alongside further safety barriers, kerbs and signage.

Stabilising adjoining earth banks differs from carriageway resurfacing because the source of potential obstruction lies outside the running surface itself. Removing loose material, stabilising a vulnerable bank and controlling water movement through the slope can require machinery and working space that cannot safely coexist with passing traffic on a confined road. The authority has therefore said another full closure will be necessary during the second phase, with precise arrangements to be announced nearer the time.

Splitting the programme into two phases allowed the reconstructed carriageway and initial drainage to reopen before winter, leaving the more extensive bank stabilisation and associated works for a separate closure. Derbyshire’s latest announcement estimates approximately 11 weeks for that second phase, while an earlier project page still refers to 12 weeks. The October programme is the more recent estimate; the authority has not yet fixed the starting date or final diversion arrangements for spring 2027.



  • Ebury Bridge phase two secures Gateway 2 approval

    Ebury Bridge phase two secures Gateway 2 approval

    Westminster has secured Gateway 2 clearance for five Ebury buildings. The council confirms five applications were approved, allowing McLaren's existing £229m contract for 334 homes to proceed.


  • A54 Cat and Fiddle road reopens after £3m upgrade

    A54 Cat and Fiddle road reopens after £3m upgrade

    Derbyshire has reopened the A54 following major road reconstruction works. The first phase finished almost three weeks ahead of schedule, while further drainage and embankment stabilisation remain programmed for spring 2027.