IN Brief:
- Wirral Council has approved John Sisk & Son's £36.5m contract for primary enabling works at Borough Yard.
- The package includes ground remediation, engineering infrastructure, an active travel connection, and part of the proposed linear park.
- The wider enabling programme is estimated at £66m, with an additional £8.9m funding requirement addressed through the Liverpool City Region Combined Authority.
Wirral Council has approved a £36.5m enabling works contract for John Sisk & Son at Borough Yard in Birkenhead, advancing preparations to redevelop a former industrial site into a new neighbourhood. The decision, taken by the council’s Policy and Resources Committee on 18 November, concerns ground remediation and engineering infrastructure on land between Birkenhead Central and Green Lane railway stations.
The 65-acre redevelopment, formerly known as Hind Street Urban Village, has planning consent for a neighbourhood incorporating up to 1,600 homes, commercial premises, community facilities, and public open space. Its location on former railway sidings and gasworks land requires extensive preparation before the proposed building programme can proceed.
Sisk’s approved contract is valued at approximately £36.5m and covers remediation and engineering works associated with the first two phases of the redevelopment. The package also includes the Mollington Link connection to the Hind Street Active Travel Corridor and the Waterloo Place section of the proposed Dock Branch South linear park. The contractor has already undertaken preparatory activities under an earlier agreement, including investigations and technical design development.
The latest appointment follows a review of the engineering requirements and costs associated with preparing the site. The overall enabling works programme is now estimated at approximately £66m, compared with an earlier budget of £57.1m. A further £8.9m funding requirement has been identified, with the Liverpool City Region Combined Authority providing additional support.
The revised financial position reflects changes to construction costs and the scope of supporting infrastructure. Site investigations have provided further information about the works necessary to address ground conditions and existing utilities, while delays and inflation have also affected the programme. The new Sisk contract forms one component of this wider expenditure rather than representing the entire cost of preparing Borough Yard for development.
Separate works will be required to relocate Cadent gas infrastructure and modify drainage assets operated by United Utilities. The latter package includes major sewer alterations and the provision of an underground attenuation tank, with expenditure estimated at approximately £13.7m. These activities fall outside Sisk’s approved primary enabling works contract and will require coordination with the wider construction programme.
The distinction between ground remediation and utility diversions is particularly important on previously industrial land. Remediation addresses contamination and other conditions associated with historic site use, while utility diversions must accommodate new development layouts without compromising existing service networks. Where major drainage infrastructure crosses proposed building plots or transport corridors, alterations may have to be completed before foundations, roads, and other permanent structures can be constructed.
Surface water management introduces another engineering requirement. The proposed attenuation infrastructure is intended to provide temporary storage within the drainage system, managing flows associated with the redeveloped site. Its final construction and operation must be coordinated with the receiving sewer network and the surrounding infrastructure, rather than treated as an isolated installation.
Wirral Council has also approved a development management agreement worth approximately £2.86m with Ion Property Developments. Ion will manage delivery of the enabling works on the council’s behalf, while Sisk’s construction responsibilities relate to the defined primary works package. The arrangements distinguish programme management from the execution of individual construction and infrastructure contracts.
Borough Yard forms part of Birkenhead’s wider regeneration programme, with the masterplan proposing new development around existing transport infrastructure. Its proximity to two Merseyrail stations provides an established public transport connection, although the site itself requires substantial changes to its internal layout and connections with surrounding roads and pedestrian routes.
The proposed Dock Branch South linear park will follow part of a former railway alignment, creating a public route through the development. New walking and cycling connections are also intended to improve access between Borough Yard and neighbouring districts. The Waterloo Place section is included in the immediate Sisk package, but other parts of the park remain outside the currently approved primary enabling works.
Highway alterations around Kings Square and further sections of the linear park have been identified for later delivery. These elements, estimated at approximately £12m, are being addressed through separate transport funding arrangements and could be incorporated into subsequent construction packages. Deferring them allows the immediate enabling works programme to progress while the wider transport infrastructure is delivered through a different sequence.
The redevelopment is expected to proceed over several years rather than through a single comprehensive building contract. Current enabling works are intended to release land supporting an initial phase of at least 633 homes, while the wider masterplan provides for further residential and commercial development. Construction of individual buildings will require the relevant land preparation, infrastructure, and detailed development arrangements to be completed.
The first phases must also be coordinated with existing infrastructure beyond the site boundary. Road access, utility capacity, surface water management, and the arrangement of development plots all influence the order in which land can be released. Completing remediation alone would not necessarily allow housing construction to begin if associated drainage or service diversions remained outstanding.
Funding for the regeneration has been assembled from several public sources, including Homes England, the Liverpool City Region Combined Authority, and Wirral Council. The revised enabling works estimate reflects the cost of preparing a complex brownfield location before substantial private development can take place. Separate transport allocations are being used to address elements removed from the immediate enabling works budget.
The committee’s approval establishes the authority to progress Sisk’s main enabling works contract, but it does not confirm completion of the remaining utility agreements or commencement of the subsequent housebuilding programme. Those activities depend on further delivery and contractual arrangements.
With the primary construction package approved, the next stages will involve finalising the relevant contractual arrangements, mobilising the works, and progressing the infrastructure required to release the initial development plots. The wider programme remains dependent on coordination between the remediation contractor, utility operators, transport infrastructure providers, and development management team.