Public construction awards total £418m in week

Public construction awards total £418m in week

Public buyers published construction contract notices worth £418.4m last week. A tally of records dated 9–15 November identifies 125 signed contracts, but some agreements predate their notices and reported values use different VAT bases.


IN Brief:

  • A tally of 9–15 November notices identified 125 signed construction contracts across 83 public buyers.
  • The contracts carried £418.4m in stated values, with a single Dungeness decommissioning contract accounting for £147m of the total.
  • Published award dates and contract values require qualification: some agreements were signed weeks earlier and the figures mix VAT-inclusive and VAT-exclusive amounts.

An analysis of the government’s Find a Tender records identifies 125 signed construction works contracts in award notices published from 9 to 15 November 2026, with a combined stated value of £418.4m. The contracts involved 83 public buyers across 118 notices. They range from large nuclear demolition works to housing maintenance and specialist roadside equipment, but publication in a single week does not mean the contracts were signed or the work started that week.

The headline figure is the total of values stated in contract notices, rather than the value of new construction work starting during that seven-day period. Buyers frequently publish their award records after contracts have been signed. The largest contract counted in this week’s total, for boiler and ancillary equipment removal at Dungeness, was signed on 23 October but published in an award notice on 9 November.

Of the 125 contracts counted, 123 carried usable stated values, adding to £418,436,001. The median among valued entries was £160,000, and 26 contracts were recorded at £1m or more. This distribution is heavily skewed towards the largest awards. A weekly sum can therefore rise sharply on the inclusion of a single major project even if the typical contract is much smaller.

At £147m, the Dungeness A boiler-removal contract accounts for more than a third of the weekly value. Nuclear Restoration Services Limited selected Aureos Highways Limited to remove eight boilers and ancillary equipment, including associated demolition, clearance and hazardous-material work. The contract was signed on 23 October, while its award notice appeared on 9 November. The contract is therefore an earlier procurement decision newly visible in the week’s public records.

Housing maintenance accounts for several of the next-largest entries. Orbit Group awarded contracts for repairs, maintenance and empty homes to IAN Williams and Cardo Group across different regions. Stated values included £46.56m for work in the South East, £42.02m in London and £30.49m in the East of England. These arrangements concern planned and responsive work on existing properties, rather than a single construction start on a new-build site.

Norfolk County Council’s £31.04m traffic signals and intelligent transport systems contract, awarded to Yunex, adds another category of infrastructure activity. Its scope includes maintaining existing signals and associated roadside equipment, together with installation and supply responsibilities. The contract was signed in October. Maintenance, renewal and technology integration sit alongside conventional civil engineering in the classification for construction work used for this count.

The count uses contracts classified by their public buyers under division 45 of the Common Procurement Vocabulary, covering construction work. It excludes notices of intended awards, supplies-only contracts and several framework or multi-supplier arrangements whose headline values are ceilings for possible future expenditure. The compiler also excluded a North London energy-recovery entry carrying an unusually large stated value because it was considered potentially a ceiling or a data anomaly; that classification is an analytical decision, not an independent ruling by the contracting authority.

Values also have inconsistent tax treatment. Twenty-four of the 123 valued contracts were published including VAT, while the remainder used figures excluding VAT. The £418.4m total adds those published amounts without adjusting them to a common basis. It is therefore unsuitable as a precise estimate of construction expenditure excluding VAT and cannot be read as the volume of activity physically delivered on sites during the week.

Regional distribution is similarly influenced by large individual entries. The South East recorded the highest combined value, at £204.8m, reflecting the Dungeness award and other contracts. The North West led by number of contracts, with 22. These rankings describe the place of work recorded in the notices, not necessarily the registered location of the successful supplier or the immediate location of site teams on the publication date.

The corresponding count for 2 to 8 November recorded 116 contracts and a combined stated value of £154.1m. Although this week’s recorded value is larger, the £147m Dungeness contract alone explains a substantial part of the difference. Contract publication times, uneven project sizes and the mixed VAT basis make that comparison distinct from a construction output index or a measure of new work beginning on site.

Dungeness decommissioning, housing repairs, road signal maintenance and smaller civil engineering schemes sit together in the public construction classification. Their award notices identify buyers, suppliers and declared contract values, while the actual construction timetable depends on each agreement. Subsequent weekly comparisons will remain sensitive to when authorities publish those records and whether unusually large or framework-related values are included.