IN Brief:
- Packaged Living and Liverpool City Council have completed a Section 106 agreement for 434 build-to-rent apartments.
- The scheme comprises two towers of 19 and 25 storeys, replacing a vacant former computer centre and hardstanding.
- A previously indicated early-2027 construction start remains a target rather than a confirmed mobilisation date.
Packaged Living has reached a further planning milestone for its 434-apartment development at Old Hall Street in Liverpool after completing a Section 106 agreement with the city council. The agreement addresses an outstanding legal requirement attached to the scheme’s planning approval, moving the proposed twin towers closer to delivery without itself confirming a construction start.
The scheme is being advanced with investment partner Affinius Capital at the junction of Old Hall Street and Leeds Street, on a site occupied by a redundant former computer centre and associated hardstanding. Packaged Living’s original planning account describes residential towers of 19 and 25 storeys, containing 434 professionally managed rental apartments. The developer has not confirmed a new start date following the completion of the legal agreement.
Liverpool’s planning committee backed the development in November 2025, subject to a legal agreement and other conditions. A Section 106 obligation can secure planning commitments associated with the development, separate from the conditions attached to the permission. Completion of the agreement is a material advance beyond the committee vote, but the remaining permission documents, discharge of relevant conditions and construction arrangements still govern how the project proceeds.
Packaged Living’s plans provide 302 apartments in the taller tower and 132 in the smaller building. The accommodation includes one-, two-, and three-bedroom flats, supported by shared resident facilities. The design has been developed by Falconer Chester Hall, with Turley involved in planning and Re-form Landscape Architecture responsible for the public-realm proposals.
The submitted design also changes circulation through the plot. A designated pedestrian and cycle route is planned through Back Leeds Street and along the northern boundary, with improved planting, lighting and active frontage at ground level. Shared facilities for residents would include lounges, workspace, a gym and landscaped roof terraces. Those amenities and public-realm works will be delivered through different parts of the overall construction programme.
The design proposes all-electric heating based on air-source heat pumps and heat recovery systems. Unlike the earlier approval and legal stages, the detailed building services programme will determine where that equipment is accommodated and how it connects with the building envelopes and electrical infrastructure. Final energy performance will depend on specification, installation, commissioning and operation once the homes are occupied.
The constrained city-centre location presents delivery interfaces beyond the two buildings themselves. Removal of the existing structure, foundation and basement works, lifting arrangements and site deliveries will have to be planned around adjoining roads and buildings. The proposed pedestrian and cycle routes will form part of the completed scheme, whereas the construction period will require temporary controls to keep the public clear of vehicle movements and lifting operations.
Before Packaged Living and Affinius Capital acquired the site in 2022, the property had been associated with the Ovatus proposals, which envisaged towers of 27 and 48 storeys. The current development is a smaller, differently configured scheme. Its 2025 committee decision and the newly completed Section 106 agreement relate to the 434-home proposal, rather than the earlier designs for substantially taller buildings.
Of the proposed homes, 302 would be in the taller tower and 132 in the smaller one. The apartments comprise one-, two- and three-bedroom units, with common amenities concentrated at ground and roof levels. Allocating residences and services between separate structures has implications for vertical circulation, plant accommodation and the construction sequence, although detailed construction methods and the principal contractor have not been disclosed in the latest update.
Designing two towers around an all-electric energy strategy will require coordination between the building envelope, heat pump equipment, heat recovery systems and electrical distribution. The planning documents establish the intended technologies, but detailed capacities and measured operational performance have yet to be demonstrated. Those matters, alongside the public realm and roof terraces, remain part of the later technical design, procurement and construction process.
Packaged Living previously envisaged demolition of the former computer centre during 2026 and the start of building work in early 2027. That programme has not been reconfirmed alongside the legal agreement, and no appointment of a principal construction contractor was identified in the November reporting. The signed agreement therefore improves the position of the planning consent without establishing a date for mobilisation.
The completion of the Section 106 agreement settles an outstanding approval-stage requirement for the development. The next verifiable construction steps will be enabling works, any remaining pre-commencement approvals, and the mobilisation of a delivery team for the two residential towers. Until those are confirmed, the 434 apartments remain a consented development proposal rather than a project under active construction.