IN Brief:
- North Somerset Council is inviting early engagement for electrical, mechanical, ventilation and insulation work at Epic Campus.
- The opportunities concern the car park and training buildings; eligible contractors need £2m annual turnover and a directly employed workforce.
- Tender invitations are expected in November 2026, with work covered by the exercise provisionally starting on site in May 2027.
North Somerset Council is inviting early engagement from specialist contractors for electrical, mechanical, ventilation and insulation packages at the Epic Campus in Long Ashton. The new opportunities cover elements of the car park and training buildings, with Somerset Chamber of Commerce handling supply chain introductions. Invitations to tender are expected in November 2026, while the work covered by this procurement exercise is expected to start on site in May 2027.
The council is looking for established companies with minimum annual turnover of £2m, a directly employed workforce and evidence of comparable commercial construction projects. Firms are being asked to demonstrate the scale and nature of previous work through case studies before the formal procurement process. The invitation is therefore a qualification and early engagement exercise, not an announcement that the packages have been awarded or that all named scopes are currently open for priced bids.
The four work disciplines are listed separately for both the car park and training buildings. The forthcoming tenders are expected to cover electrical supply and installation, mechanical systems, ventilation, and insulation, but the council has not specified individual package values or issued detailed equipment and materials schedules in the engagement notice. Scope boundaries and installation interfaces will therefore need to be confirmed in the formal tender documents before contractors can price programme risk, access requirements and commissioning responsibilities.
Gilbert-Ash is the main contractor for the wider Epic Campus, which occupies land between the A370 Long Ashton Bypass, Colliters Way and the railway line. The planned development includes five office buildings, a 3,000-seat auditorium, a culinary building, a training facility and site infrastructure. North Somerset Council gives an overall gross internal floorspace of approximately 104,545 square metres, including car parking and service buildings. The November engagement concerns only selected specialist packages within that much larger, phased construction programme.
Work on the earlier campus phases is already progressing, including site access, utilities and the first office building. The council reports completed diversion of the overhead power line underground, establishment of fencing and haul roads, and substantial excavation for utility buildings and the first office basement. A ground floor slab has been poured for part of the first office block, and vertical core construction has begun. Those operations are separate from the car park and training building packages currently approaching tender.
Electrical and mechanical installation will involve differing building requirements. A car park may require ventilation, lighting, electrical distribution and safety systems appropriate to vehicle circulation, while a training facility has occupied rooms with different internal environmental and servicing needs. The installation trades will need to coordinate plant positions, cable and duct routes, structural openings and access for testing. The council has not published the relevant system capacities, final equipment selections or individual commissioning obligations for these particular packages.
The forthcoming contracts also sit within a wider programme that includes two utility buildings, site-wide drainage, public realm, access roads and landscaping. North Somerset Council describes a basement car park planned for 536 spaces, alongside cycle and motorcycle parking. Utility connections and logistics arrangements across the site will affect later construction access even where the package boundaries are confined to building interiors. The project’s phased structure makes coordination between main contractor, early works contractors and incoming specialist teams an important part of delivery.
The approved landscape strategy retains approximately 13.8 hectares of the northern site without above-ground development as a green wedge. Proposals also include re-naturalising Ashton Brook, creating public parkland, and retaining or realigning existing rights of way. Permanent vehicle access is planned from the Gurney roundabout on the A370 and from Colliters Way. These restrictions and interfaces form part of the wider site logistics picture, although no landscaping or highway package award is included in the November building services invitation.
The November round follows earlier supply chain activity. North Somerset Council outlined opportunities including scaffolding, brickwork and drylining in August, while an October update reported further packages and introductions of regional businesses to Gilbert-Ash and Kane Group. This latest engagement focuses on specified electrical, mechanical, ventilation and insulation work, with tender invitations expected during November. It is a further phase of procurement rather than the first occasion contractors have been invited to participate in the development.
Somerset Chamber of Commerce is coordinating the brokerage and introductory process before formal tendering. Eligibility requirements include at least £2m annual turnover, directly employed workers and evidence of comparable commercial projects, as stated in the council’s notice. The threshold may exclude some smaller subcontractors despite the emphasis on local supply chains. Companies expressing interest have not been awarded the work; the tender invitations, final scope documents and appointment decisions have yet to follow.
The next procurement milestones are the issue of invitations, clarification of work boundaries and selection of contractors for the specified systems. May 2027 is the council’s projected start for the work described in this engagement, not the commencement date of the entire campus, where construction is already in progress. Technical coordination will be especially important between incoming specialist contractors and Gilbert-Ash’s ongoing enabling and building programme as the later phases are brought forward.