IN Brief:
- The council’s preferred option allocates £86.88m in new capital expenditure for the combined programme.
- The works include replacing the Corn Exchange roof and addressing deteriorating fabric and services at the Guildhall.
- Market Square is expected to be completed in March 2028, with wider public realm works continuing until August 2029.
Cambridge City Council has approved the refurbishment of its Civic Quarter, enabling main contractor Sir Robert McAlpine to prepare for construction across the Guildhall, Corn Exchange, Market Square, and adjoining streets. The council’s preferred option provides for £86.88m in new capital expenditure, with construction due to begin in January 2027.
The decision on 26 November follows assessment of four options for the future of the civic buildings. Each included investment in the Corn Exchange and market, but differed in its treatment of the Guildhall. The council selected the full refurbishment programme incorporating value engineering measures developed during the project’s design and financial assessment.
The capital allocation covers new expenditure rather than a single building contract. Council documents identify a separate option involving minimum necessary works to the existing assets at a cost of approximately £69m. The council considered the longer-term financial effects of those alternatives as well as their immediate construction costs, including the income the refurbished properties could generate.
Cartwright Pickard is leading architectural design for the scheme. Planning and listed building consents for the Guildhall and Corn Exchange were granted in March 2026; the Market Square and public realm proposals received planning approval in September. The construction programme will initially concentrate on the two buildings while arrangements for temporary market trading progress.
Surveys of the Guildhall identified water ingress affecting upper floors, damage to existing finishes, and deterioration of parts of the building fabric, including the roof structure over the council chamber. The building also requires work to ageing electrical and fire safety installations, together with corroding heating infrastructure.
The combined refurbishment creates an opportunity to coordinate the repair of those systems with changes to the building’s internal accommodation. Replacing heating equipment without addressing its distribution infrastructure, for example, could leave deteriorating pipework in service. Coordinating access to ceilings and service routes allows contractors to assess interconnected systems while the building is undergoing more extensive construction.
The council’s design proposals would also make the historic chamber usable by a wider range of occupants and activities. Fixed furniture would be removed from the chamber and retained elsewhere in the Guildhall, enabling changes to circulation and room layout without discarding the original pieces. The proposals take account of possible changes in the building’s civic function following local government reorganisation.
At the Corn Exchange, the most substantial identified building envelope requirement is replacement of the roof. The council also intends to improve ventilation, accessibility, and energy efficiency while upgrading facilities for performers and visitors. The venue has been an established part of the city’s cultural infrastructure for more than 150 years.
A roof replacement within a retained building requires the construction team to coordinate opening up, structural repairs, and temporary weather protection. Existing fabric must remain protected while new materials are installed; the thermal and moisture characteristics of the replacement assembly also need to be compatible with the retained structure. The detailed roof construction methodology has not been announced.
The Market Square design will retain and relay Victorian granite setts to improve access across surfaces that currently present difficulties for wheelchair and pushchair users. The revised proposals provide 55 permanent stalls, rather than the 27 originally proposed, comprising 43 lockable units and 12 open stalls. Integrated electrical supplies and lighting are planned, together with solar panels or green roofs on some units.
The stall layout makes the provision of services beneath and around the market an important component of the construction programme. Reusing the historic paving while improving levels and accessibility requires coordination between surface installation, drainage, and the underground services supplying the trading areas. The council has identified existing electricity and water infrastructure as requiring improvement.
Market traders are expected to move progressively into nearby streets between January and April 2027, subject to planning approval for temporary trading. Retaining trading within the immediate area will require separation between construction traffic, pedestrians, and servicing movements, alongside the establishment of suitable temporary infrastructure.
The planned construction sequence anticipates completion of Market Square in March 2028 and the Corn Exchange during the summer of that year. The Guildhall is expected to follow in December 2028, with improvements to streets and connecting public spaces continuing until August 2029.
The combined programme allows the council to address condition-related works and the wider changes to the quarter through a coordinated delivery strategy. The contractor will have to balance building refurbishment, specialist conservation, market relocation, and public realm works while maintaining access to the surrounding city centre throughout the phased programme.



