IN Brief:
- The university has entered into a construction agreement with GRAHAM after securing funding from government and Cumberland Council.
- Main construction is expected to start in early 2027, with the university targeting an opening in 2029.
- The first phase incorporates teaching and student facilities, a business exchange centre, and public realm improvements.
GRAHAM has secured a construction contract with the University of Cumbria for its Carlisle Citadels campus, moving an £85.2m redevelopment programme towards main construction in early 2027. The project will integrate new university accommodation and business facilities with the retained sandstone frontage of a former department store in the city centre.
The funding package includes support from the Ministry of Housing, Communities and Local Government through the Borderlands Inclusive Growth Deal, together with more than £5.2m from Cumberland Council through the Carlisle Town Deal Fund. The university confirmed the construction agreement on 26 November after securing funding from its principal project partners.
The £85.2m allocation relates to the development as a whole. GRAHAM’s individual contract value has been reported at £55m by Construction Enquirer, although the university has not separately confirmed that figure. A further £1.4m grant proposal is due to be considered by Cumbria Combined Authority on 30 November.
Construction will take place next to Carlisle railway station, on a site that includes the former Woolworths building on English Street and Victoria Viaduct. The 1930s sandstone frontage will be preserved while the buildings behind it are demolished and replaced. GRAHAM expects temporary support structures and traffic management measures to remain in place for much of the construction period.
Retaining a façade while removing its supporting building requires a different demolition sequence from conventional site clearance. Existing floors and internal walls may provide lateral restraint to masonry; once they are removed, temporary supports must maintain the wall’s stability under wind loading and other forces until the new permanent structure can take over.
The supports also have to accommodate the existing condition and geometry of the sandstone façade. Connections to retained material require care to avoid damaging the features being preserved, while construction tolerances must allow the historic masonry to be integrated into a new building frame. The contractor has identified the restricted city centre location as an additional engineering challenge.
The university’s revised proposals follow changes to the phasing of the development earlier this year. Plans approved in May deferred a new five-storey teaching building at the southern end of the site to a subsequent phase, enabling the immediate programme to concentrate on the first stage of the campus. The latest opening target is 2029, for students entering the 2029–30 academic year, subject to outstanding approvals and agreements.
The initial scheme is designed to accommodate digitally enabled teaching spaces, student support services, a café, informal learning areas, and the Carlisle Business Exchange. The university’s published project information describes approximately 8,000 square metres of first-phase space, alongside work to the surrounding public realm. The business exchange is intended to provide premises where local businesses and university staff can work together.
Cumberland Council approved arrangements for grant funding and the disposal of land on English Street in September. The council’s executive records identify an 800-square-metre business exchange centre, supported by Town Deal funding, with workspace intended for new and growing companies. The development will therefore bring commercial workspace and teaching functions into a single project close to the railway station.
Those uses have differing demands on the building services design. Teaching rooms require appropriate ventilation, acoustic separation, and communications capacity, while shared business accommodation needs sufficient flexibility to accommodate changes in occupancy and layout. Coordinating the distribution of services with the structural design will be particularly important around the retained building fabric, where the available routes and fixing locations may be constrained.
The public realm programme must also connect the new campus entrances to surrounding streets and existing pedestrian routes. Temporary construction access and material deliveries will have to be coordinated with the operating railway station and neighbouring commercial premises, particularly while façade retention structures occupy space close to the highway. The university has asked the public to allow for disruption while those arrangements are established.
The Citadels investment is one of the major regeneration projects within the wider Borderlands programme, which supports economic development across the English and Scottish border region. Bringing the university’s facilities into central Carlisle links the construction of education infrastructure with the redevelopment of existing property and the provision of workspace for regional employers.
With the principal construction agreement in place, the next milestone is the commencement of main works. The university’s 2029 opening target leaves a programme covering demolition, heritage protection, permanent structural construction, building services, fit-out, and commissioning, with the transition from temporary to permanent support forming a critical interface in the construction sequence.