IN Brief:
- Procurement has become slower for 60.2% of respondents to a survey of public sector professionals.
- Heavier administrative requirements were reported by 87.5% of respondents, rising to 92.8% in local government.
- Just 15.7% of respondents consider their procurement teams fully resourced and capable of operating effectively under the Act.
More than three in five public sector professionals report that procurement has become slower since the Procurement Act 2023 took effect, according to research by Pagabo examining the transition to the new regime across organisations responsible for housing, education, infrastructure, and other public services.
The procurement specialist partnered with Surveys in Public Sector to consult 87 individuals from 80 organisations between 21 May and 14 August 2026. Respondents included professionals working in procurement, estates, asset management, finance, and other public sector functions. The findings reflect their reported experiences rather than an independent measurement of elapsed tender times.
Overall, 60.2% said procurement was significantly or somewhat slower than before the Act came into force on 24 February 2025. Another 24.1% reported broadly unchanged timescales, 13.2% were unable to assess the effect, and just 2.4% reported an improvement.
Longer timescales were reported by 72.2% of housing association respondents and 62.1% of local government respondents, compared with 30% in education. Both housing associations and local authorities commission substantial construction and maintenance programmes, although the individual sector samples are small and the survey does not isolate procurement for building works from other expenditure.
Administrative workloads have increased for 87.5% of respondents compared with the previous Public Contracts Regulations 2015 regime, with 60% describing the increase as significant. In local government, 92.8% reported a heavier burden. Only 14.5% of respondents said they were managing all transparency requirements without difficulty.
Preparing and publishing notices was the most commonly identified bottleneck, cited by 56.6%. Internal approvals and governance sign-off followed at 48.2%, while evaluation and moderation, and the design of bespoke competitive flexible procedures, were each cited by 39.8%. Contract detail notices were identified as particularly burdensome by 47%.
Under the Act, contracting authorities can conduct an open procedure or design a competitive flexible procedure proportionate to the nature, cost, and complexity of the contract. A construction competition can therefore incorporate several stages, allowing an authority to assess proposed technical solutions before inviting final tenders. The authority must establish the procedure and its requirements through the tender documentation.
Only 6% of surveyed professionals said the competitive flexible procedure had substantially improved flexibility in practice. Another 31.3% saw little difference from earlier arrangements, while 26.5% were either unable to assess the procedure or had not yet found it applicable. Designing and administering a bespoke competition requires commercial and technical resources that may already be committed to managing existing contracts.
Pagabo itself is introducing early contractor engagement arrangements through its £5bn National Framework for Major Works, with six contractors appointed to provide collaborative partner services. Such arrangements can help clients establish design requirements, programme constraints, and delivery risks before committing to construction, although the framework’s maximum value does not represent guaranteed expenditure.
The survey found that only 15.7% of respondents considered their procurement teams fully resourced and capable of operating effectively under the Act. Where technical specialists are required to support tender evaluation, procurement capacity also depends on whether the authority can release those specialists from existing estate management and project responsibilities.
Transitional provisions add a separate administrative requirement. Contracts and frameworks procured under earlier legislation generally continue to be governed by that regime. A public body managing a legacy construction framework alongside newly procured agreements must therefore maintain procedures suited to both sets of rules, rather than applying the new provisions retrospectively.
Support for the legislation remains considerably stronger than confidence in its ability to reduce workloads. Some 60.9% of respondents agreed that the Act was a positive step for public procurement and 71.2% described their implementation as somewhat or very successful. Nevertheless, 51.7% said the transition had been harder than anticipated.
Only 20.9% expected the Act to deliver long-term efficiency savings, compared with 44.2% who disagreed. Greater flexibility was still identified by 21.2% as the aspect most likely to have a positive impact over the next three years, followed by transparency and open data at 18.8%.
A prolonged competition can affect construction delivery even before a contractor is appointed. School refurbishment programmes, for example, may be planned around holiday periods, while infrastructure schemes often require coordinated access and specialist subcontractor availability. If a contract award moves beyond its original date, the available construction window can narrow or the start of work may need to be rescheduled. The survey does not quantify those downstream delays, but its findings identify the procurement activities where authorities are encountering the greatest pressure.