NHBC housing starts fall 7.2% in England

NHBC housing starts fall 7.2% in England

NHBC housing starts fell across England during the third quarter. Savills reports a 7.2% annual decline in that series, while separate EPC data show 199,400 new homes completed during the year to Q3 2026.


IN Brief:

  • NHBC housing starts were 7.2% lower than a year earlier and slipped 1.2% from the previous quarter.
  • EPC data indicate 199,400 completed homes in the year to Q3 2026, while full consents remained historically subdued.
  • Planning delays, material costs, and weaker sales conditions continue to restrict the conversion of sites into active construction.

Housing starts in England were 7.2% lower year on year in the third quarter of 2026, according to the National House Building Council series examined by Savills. A separate Energy Performance Certificate measure puts new homes completed in the year to Q3 at 199,400. The figures show weaker activity at the beginning of the construction pipeline even while schemes started in earlier years continue to reach completion.

Using National House Building Council data, Savills found that starts were down 1.2% from the previous quarter as well as 7.2% on an annual comparison. Private housing starts declined by 6.7% from a year earlier, while alternative tenures, which include affordable housing and build-to-rent, recorded an 8.1% annual fall. The rates refer to that housing-starts series, not to every measure of new homebuilding published by government.

Energy Performance Certificate data indicate 199,400 new homes completed in the twelve months to Q3. That is 1.0% below the preceding rolling annual figure, although 1.3% above the comparable period a year earlier. The different comparisons need to be read together: the latest quarterly movement is weaker, but the annual total has not fallen in every year-on-year comparison.

Completions measure the endpoint of work begun many months or years before, whereas starts provide an earlier indication of the flow of construction entering the pipeline. A sustained reduction in starts can therefore lead to lower completions later even if sites already under construction continue to reach handover. Labour demand, subcontract packages, and materials purchasing can also change at different stages of that sequence, rather than moving in lockstep with completions.

About 215,000 homes gained full planning consent in the year to Q3 2026, according to preliminary Glenigan and Home Builders Federation data used by Savills. The total was broadly unchanged from the previous quarter but more than 5% lower than a year earlier and 36% below its June 2021 peak. In four of England’s nine regions, the annual number of consented homes was lower than the number completed.

Planning permission does not automatically release a site for construction. Pre-commencement conditions, legal agreements, infrastructure requirements, remediation, utility connections and scheme viability can all affect when a contractor can start. A persistent imbalance between the number of homes receiving consent and those being completed can leave the forward pipeline thinner, although individual developments move through the process at very different speeds.

Rising build costs are putting further pressure on schemes awaiting a start. Savills cites BCIS data showing a 23% increase over five years and an NHBC sentiment survey in which 89% of responding developers identified planning delays as a constraint. Materials costs were cited by 51%, and labour costs by 36%. These are developer assessments of obstacles in Q2 2026, rather than a measurement of the price change on every project.

The survey also distinguishes rising prices from shortages. Respondents generally identified the cost of labour and materials as a greater obstacle than their availability, meaning projects can remain commercially difficult even where suitable contractors or products can be sourced. Land values, borrowing conditions and expected sales revenue then influence whether the development can proceed under its existing appraisal.

Official construction output data provide a related but different view of the market. The Office for National Statistics estimated a 4.7% contraction in private new housing work during Q3, contributing to a 0.7% fall in total construction output. September alone showed a monthly output increase of 0.8%, demonstrating that a single month’s improvement can coexist with a weaker quarterly trajectory.

Delivery is concentrated among larger developers. Savills estimates that the ten biggest housebuilders completed 57% of homes in its Q3 assessment, with builders ranked 11 to 50 accounting for 28% and companies outside the top 50 delivering 15%. Smaller housebuilders have a narrower portfolio over which to spread pre-construction expenditure, and a delayed consent or unviable site can therefore have an immediate effect on their work programme. Recent survey findings among smaller developers have also shown substantial project delays.

Official building-control statistics provide another measure of housebuilding starts, but the government’s April–June 2026 series covers a different period and reporting system. It cannot be directly merged with NHBC’s subsequent Q3 figures. The 7.2% fall is specifically an annual change in the NHBC series analysed by Savills, while the 199,400 completions estimate comes from EPC records and covers a rolling year.

The immediate pressure is on the movement of viable schemes into construction. Completions over the next year will still include homes started before the latest decline, but a thinner stream of NHBC starts and relatively low full planning consents reduce the volume of work moving towards subsequent handovers. Savills expects the weakened starts pipeline to weigh on near-term housing delivery.