HS2 begins Curzon viaduct deck installation

HS2 begins Curzon viaduct deck installation

HS2 is beginning deck installation on Birmingham’s Curzon approach viaducts. A 125-tonne gantry crane will position 1,516 precast concrete slabs over 18 months, linking progress on the structures to the next railway construction phase.


IN Brief:

  • A gantry crane weighing 125 tonnes will install 1,516 reinforced concrete slabs on the Curzon approaches.
  • The precast units are manufactured in Kingsbury, where production has moved from Delta Junction segments to the Birmingham deck programme.
  • The 18-month installation sequence will require overnight restrictions on the A4540 as work proceeds above the road.

HS2 is beginning installation of the concrete decks across its Curzon approach viaducts in Birmingham, with a 125-tonne gantry crane positioned above Lawley Middleway for an 18-month programme of precision lifting. The operation will place 1,516 reinforced concrete slabs on the elevated structures that carry the railway towards the new Curzon Street terminus.

The deck installation follows the construction and launching of the viaduct structures themselves. Five interconnected viaducts form the approaches, although the newly positioned gantry is scheduled to work in sequence across Lawley Middleway, Curzon 2, Curzon 1, and Duddeston Junction. The slabs will form the permanent running decks before the railway systems and track can be installed.

The Kingsbury plant’s purpose-built casting operation will continue after its workforce completed the Delta Junction production run. The 140-strong team previously spent four years making 2,742 viaduct segments, and has now switched to the reinforced slabs required for Curzon. The change keeps experienced precast workers and factory facilities active while the major civil engineering programme moves between different Birmingham structures.

Factory production allows reinforcement, formwork and casting to be organised before an individual viaduct span is ready to receive its deck. Installation will still require careful control of lifting positions and connections between the slabs and their supporting structures. As the work is taking place above urban roads and walkways, the programme must coordinate concrete delivery and lifting with traffic management and exclusion zones below the workface.

Using a travelling gantry for repeated lifts changes the work sequence from a series of isolated crane operations into a progressively advancing installation. The 125-tonne machine has been lifted into position above Lawley Middleway and will move through Curzon 2 and Curzon 1 before reaching Duddeston Junction. The next structure must be prepared before the gantry can advance, while the flow of completed slabs from Kingsbury must match the installation programme.

Greg Sugden, HS2 Ltd’s head of delivery for the Curzon approaches, described the operation as the final major phase of civil engineering on this section of the railway. He called it “a test of skill and precision”, with each structure needing to be ready before deck installation starts. HS2 expects the elevated approach to be structurally complete once the slabs have been laid, leaving the railway track and systems programme to follow.

The most immediate disruption will be on the A4540 Lawley Middleway between Garrison Circus and Curzon Circus, where the gantry must work above carriageways and public walkways. Northbound overnight closures are scheduled from 21 November to 6 December, with both directions closed overnight between 25 November and 2 December. Southbound-only overnight closures are then planned between 3 and 6 December. The stated closure hours are 10pm to 6am, and the overlapping dates reflect successive traffic management arrangements rather than uninterrupted daytime closure.

The overnight restrictions reflect the conditions of lifting above a live highway. Traffic must be removed from the area beneath the work, while the placement sequence and movement of lifting equipment are coordinated with temporary access arrangements. The closures are limited to specified night-time periods rather than a continuous closure throughout the installation programme, allowing normal use of the road outside the published restrictions.

The Curzon approach is made up of five interconnected viaducts, but the gantry’s announced route covers four named structures. The fifth, Curzon 3, is closer to the terminus and has a wider form as the alignment approaches the station platforms. Work on these different structures has taken place in separate phases, so the start of slab installation should be understood as progress on the elevated approaches rather than completion of every part of the railway into the station.

Earlier Birmingham HS2 work included the launching of the separate M6 South viaduct. Its final structural launch was a distinct milestone involving the movement of an assembled bridge structure. The Curzon operation uses precast slabs to establish permanent decks on structures that have already been erected or launched, after which the rail installation and fit-out teams can take over.

HS2’s stated programme allows around 18 months for the 1,516 placements. Production at Kingsbury, readiness of each individual viaduct, and access above Lawley Middleway will govern the work until the gantry reaches Duddeston Junction. Structural completion of the elevated approaches is planned to follow the deck installation, ahead of the separate railway track and systems phases.