St Helens clears Parkside phase two works

St Helens clears Parkside phase two works

St Helens has backed phase two at Parkside Colliery site. The hybrid consent opens the way for enabling, access, drainage, and infrastructure works across the former colliery at Newton-le-Willows, supporting a further tranche of logistics and manufacturing floorspace within the Liverpool City Region Freeport.


  • Hybrid planning consent covers enabling works and up to c.160,000 sq m employment space.
  • Outline elements target B8 logistics plus B2 and E(g) manufacturing uses.
  • Infrastructure delivery, including access via the Parkside Link Road, is now the near-term focus.

Planning permission for phase two of the Parkside Colliery regeneration in Newton-le-Willows has been agreed, moving the development into an infrastructure-led delivery phase designed to unlock the next wave of industrial and manufacturing build-out.

The phase-two application combines a full element for enabling and sitewide works with outline consent for new employment buildings. The enabling scope covers the type of heavy, unglamorous activity that dictates whether a brownfield scheme can move at pace — earthworks to establish development platforms, strategic drainage and groundworks, landscape planting, ecological and noise mitigation measures, and the internal circulation and servicing that turns a large parcel of land into something contractors can actually build on.

In parallel, the outline component seeks consent for employment floorspace primarily aimed at B8 logistics, plus B2 and E(g) manufacturing and industrial uses, with ancillary office space. The submitted parameters indicate up to around 160,000 sq m of floorspace, which places phase two in the same scale bracket as the UK’s larger regional shed-and-manufacturing allocations rather than a standard local employment site.

Access is tied to the Parkside Link Road, which has been positioned as the practical gateway for the western side of the wider Parkside allocation. That matters operationally because it dictates how quickly a site can support construction traffic, then HGV movements, without back-loading risk onto local roads and junction upgrades that can drag programme and budgets.

The Parkside site sits inside the Liverpool City Region Freeport geography, adding a further layer of interest for occupiers weighing total landed cost, labour access, and planning certainty. Freeport status does not build buildings by itself, but it can sharpen the commercial case for logistics and light industrial operators when combined with motorway connectivity and developable platforms on a large site.

For contractors and enabling specialists, the immediate workload is straightforward — civils, drainage, utilities interfaces, remediation, and landscape delivery — but the sequencing will be watched closely. On sites of this scale, platform creation and water management are rarely “background” items; they are critical-path activities that decide whether follow-on packages can tender cleanly and mobilise without early claims and redesign.



  • Construction slump deepens in February PMI

    Construction slump deepens in February PMI

    February data showed UK construction activity retreating faster again nationwide. The headline PMI fell to 44.5 as weak demand, wet weather, and a sharper housebuilding downturn weighed on output.


  • JCT updates Contracts Discovery for 2026

    JCT updates Contracts Discovery for 2026

    JCT has published a revised Contracts Discovery module for 2026. The updated teaching resource aligns with the JCT 2024 contract suite, adding new content on procurement routes, contract setup, and key obligations across delivery.