Wimbledon scheme switches from offices to co-living

Re:shape has revised Wimbledon plans around a housing-led mixed-use scheme. The proposal replaces an unbuilt office consent with 532 co-living studios, 36 social-rented homes, and commercial space.


IN Brief:

  • The proposal contains 532 co-living studios, 36 social-rented homes, and 2,271 sq m of workspace.
  • A vacant office block and unbuilt 2023 consent would be replaced by a housing-led mixed-use scheme.
  • Planning determination, mayoral comment, construction funding, and a main contractor remain outstanding.

Re:shape has submitted revised plans for a mixed-use redevelopment in Wimbledon, replacing an unbuilt office-led consent with 532 co-living studios, 36 social-rented homes, workspace, and ground-floor commercial accommodation.

The application covers St George’s House East on St George’s Road, opposite Wimbledon station. The existing late-1980s office building would be demolished and replaced by a taller scheme designed by PLP Architecture, with the main element rising to 13 storeys.

A 12-storey office development was approved on the site in 2023 but did not progress to construction. The latest proposal changes the development model rather than merely adjusting the approved design, introducing managed residential accommodation alongside affordable housing and a smaller but still substantial employment component.

The plans include 2,271 sq m of Grade A workspace, active commercial uses at street level, and flexible space intended for local businesses and community organisations. Cycle parking, public-realm improvements, energy-efficient building systems, and biodiversity measures also form part of the submission.

Housing-led design resets the delivery brief

Switching from offices to co-living changes the structural, servicing, fire, acoustic, and operational requirements of the building. A workplace can accommodate large, adaptable floorplates, whereas several hundred studios require repeated partitions, bathrooms, drainage connections, ventilation routes, metering, access control, and a much denser pattern of occupation.

Shared amenity areas become part of the residential product and must be integrated with circulation, management, cleaning, maintenance, and fire strategy. The project also combines different tenures and uses, requiring sufficient separation without creating inefficient duplicate systems or awkward servicing arrangements.

The 36 social-rented family homes add another design and delivery layer. Their layouts, access, amenity, and management requirements differ from the co-living studios, while planning obligations and funding conditions may influence how the affordable element is phased, transferred, and maintained.

The revised proposal reflects the viability pressures facing speculative office development outside the strongest central London submarkets. An approved design does not create construction activity unless occupier demand, rents, finance, and build costs support a fundable project. Changing use can revive a stalled site, but it also requires a fresh planning case and substantial redesign expenditure before procurement can resume.

Wimbledon’s transport connections support a high-density residential model and reduce the need for extensive car parking. The station location also creates construction constraints, including restricted delivery routes, heavy pedestrian flows, neighbouring businesses, railway interfaces, noise controls, and limited space for materials storage or large compounds.

Demolition of the existing office block will need to account for adjoining properties and a busy town-centre environment. Surveys must establish the structural form, hazardous materials, service connections, and the potential for reuse or recycling before the main works sequence can be finalised.

The stepped crown and Art Deco references are intended to address the building’s scale within the Wimbledon townscape. For the delivery team, the more practical challenge will be translating that external form into repeatable façade zones, weatherproof details, maintenance access, and interfaces that can be manufactured and installed efficiently.

The project is targeting BREEAM Excellent, although final performance will depend on the selected structure, envelope, services, controls, materials, and operational assumptions. High-density residential accommodation places sustained demand on hot water, ventilation, lifts, waste handling, and communal facilities, so energy modelling must reflect actual occupancy rather than office-based benchmarks inherited from the earlier consent.

The consultant team includes Whitby Wood for structural engineering, Applied Energy for building services, Orion Fire, BB7 for façade advice, and KS4 for quantity surveying. That breadth indicates the level of coordination required before planning approval can be converted into a construction package.

The application remains under consideration, and planning determination, mayoral involvement, construction funding, and appointment of a main contractor are outstanding. The scheme should therefore be treated as a proposed redevelopment rather than an imminent start on site.

Cost planning will be central to the next stage. The development must support hundreds of serviced units, substantial shared space, affordable homes, commercial accommodation, and a high-quality external envelope on a constrained site. Value engineering that reduces capital cost without undermining durability or operational performance will require early agreement between the developer, operator, design team, and future contractor.

Procurement will also have to account for the repetitive nature of the residential content. Bathroom pods, service modules, prefabricated risers, or other standardised elements may offer programme advantages, but only where the design is sufficiently stable and the logistics of a constrained urban site can support them.

The revised application returns to a site that already carries one approved but unbuilt proposal. The housing-led model may offer a stronger route to delivery, but the meaningful milestone will not be another consent. It will be a funded contract capable of moving the scheme from drawings into construction.