Calverley Close phase two moves into construction

Calverley Close phase two moves into construction

Vistry has started construction on Calverley Close’s second regeneration phase. The 32-home social-rent package forms part of the wider 275-home Bromley estate redevelopment.


IN Brief:

  • Riverside and Vistry are delivering another 32 social-rent homes at Calverley Close.
  • The 275-home regeneration will replace 163 existing properties through a phased occupied-estate programme.
  • Current reporting targets spring 2028 for phase-two completion, later than Riverside’s earlier Block 2A programme.

Vistry Group and Riverside have moved the second phase of the Calverley Close regeneration in Bromley into construction, with Countryside Partnerships delivering another 32 homes for social rent. A groundbreaking ceremony on 13 August marked the latest stage of the 275-home redevelopment, which is replacing the existing estate through a phased programme intended to keep current residents within the neighbourhood.

The second phase follows demolition and enabling work undertaken earlier in 2026. Riverside reported in February that properties at 3–17 Calverley Close had been demolished and that preparation for Block 2A would include crushed-material processing, a water diversion, temporary parking, surveys, piling, and drainage.

At that point, Riverside expected groundworks to begin in late March and Block 2A to complete in autumn 2027. Current coverage of the phase-two groundbreaking gives spring 2028 as the expected completion date for the 32 homes, indicating that the public programme has moved since the earlier resident update.

The difference is worth recording because phased estate regeneration depends on handovers occurring in the right order. A completion date is not simply a commercial milestone when existing households are waiting to move into the new properties before older homes can be released for demolition and subsequent phases.

The wider Calverley Close redevelopment will provide 275 homes, comprising 179 for social and affordable rent and 96 for private sale. It replaces 163 existing homes, while Vistry’s earlier masterplan information describes 255 apartments across six blocks of six to seven storeys together with 20 three-storey townhouses.

Residents backed the redevelopment in a ballot in July 2021, and full planning permission followed in 2023. The programme is supported by Greater London Authority grant funding, with existing social tenants offered replacement homes on the rebuilt estate while retaining their tenancy and rent terms.

The first phase demonstrated the mechanics of that approach. Riverside completed 18 new social-rented homes in October 2025, with adapted properties for residents with particular mobility requirements following within the wider first-phase programme. New landscaped communal areas, pocket parks, and a children’s playground were also delivered.

That initial handover was important because the project cannot progress as though Calverley Close were an empty development site. Existing residents, retained homes, temporary access, utilities, demolition zones, and new construction all have to coexist while households move progressively from old properties into completed ones.

Phase two therefore carries programme dependencies that extend beyond the construction of 32 flats. Homes have to be finished, commissioned, snagged, handed over, and ready for occupation before resident moves can unlock the next sections of the estate. A delay at handover can subsequently affect demolition dates, temporary works, utilities, and the release of later workfronts.

This makes occupied-estate regeneration particularly sensitive to sequencing. A contractor can recover some lost production on a straightforward new-build site by adding resources or changing trade sequences, but there is less flexibility when the next physical area cannot become available until households have moved.

The homes themselves are intended to improve space, accessibility, and energy performance compared with the estate being replaced. Those objectives create another set of delivery requirements around fabric, heating, ventilation, commissioning, accessibility, and resident familiarisation, especially where households are moving directly from older stock into unfamiliar systems.

Riverside’s earlier updates show the level of attention already being given to final inspections, snagging, home demonstrations, meters, and heating systems. Those activities can look peripheral beside piling and structural work, but they determine whether a completed building is actually ready to receive residents and release the next demolition zone.

The regeneration also has a long overall programme. Earlier Vistry material places completion of the full 275-home scheme in the 2030s, exposing later phases to future changes in regulation, labour, material costs, and market conditions. Repetition across the blocks should provide opportunities to carry design and delivery learning forward, although a long programme also creates more time for assumptions to change.

For the current phase, the immediate task is narrower: turn the cleared and prepared site into 32 social-rent homes while maintaining the resident and construction sequence around it. Current reporting now points to spring 2028 for completion, rather than Riverside’s earlier autumn 2027 Block 2A target. On a phased occupied estate, that six-month difference matters well beyond one block.