Avantium closes Worley contract at Delfzijl plant

Avantium closes Worley contract at Delfzijl plant

Avantium has closed Worley’s construction contract for its Delfzijl plant. The agreement resolves outstanding EPC matters as commissioning moves into commercial preparation.


IN Brief:

  • Avantium and Worley signed a close-out agreement on 29 September covering the construction phase of the Delfzijl FDCA plant.
  • The settlement addresses outstanding invoices and claims, remediation responsibilities, titanium welding matters and EPC contractual close-out.
  • All major process units have been commissioned and first FDCA has been produced ahead of planned commercial deliveries.

Avantium has completed the contractual close-out of the construction phase of its FDCA flagship plant at Delfzijl in the Netherlands, resolving the principal outstanding commercial and technical matters with engineering, procurement and construction partner Worley.

The companies entered into a close-out agreement on 29 September covering outstanding invoices and claims, responsibilities associated with remediation activities, titanium welding matters and the formal conclusion of the EPC relationship. Avantium said the agreement also establishes a framework for future cooperation.

The settlement follows a prolonged construction and commissioning programme at the first commercial-scale plant built around Avantium’s proprietary process for producing furandicarboxylic acid, or FDCA.

FDCA is intended as a feedstock for polyethylene furanoate, a polymer being commercialised by Avantium under its releaf brand. The Delfzijl facility is designed to move the company’s technology beyond pilot operation and demonstrate the process at industrial scale.

The route to start-up has included significant remediation work. Earlier in 2026, Avantium identified construction-related issues affecting titanium welds within the plant, leading to a specialist repair programme before the affected process equipment could move through the remaining commissioning stages.

Those repairs were subsequently completed and commissioning continued across the plant. Avantium announced earlier this week that all major process units had been commissioned and that the first batch of FDCA had been successfully produced.

The 29 September close-out is therefore a separate construction milestone rather than a repeat of the first production announcement. Producing material establishes that the process has operated through the required stages, while the agreement with Worley addresses the unresolved contractual and remediation matters associated with delivery of the plant.

Large process projects rarely move directly from construction completion to routine commercial operation. Mechanical completion, testing, commissioning, defect correction, performance verification and commercial settlement can follow different timetables, particularly where specialist equipment or material issues emerge during start-up.

The titanium welding work is a case in point. Titanium is used where resistance to corrosive process conditions is required, but fabrication quality is critical because defective welds can compromise the integrity of pipework or equipment exposed to aggressive media.

Repairing such defects is therefore more than ordinary snagging. The affected work needs specialist procedures, inspection and quality assurance before equipment can be released safely into commissioning, and any delay can affect the sequence of downstream systems that depend on that part of the process.

With those repairs completed and all major process units commissioned, Avantium is now focused on additional FDCA production, product qualification and preparation for its first commercial deliveries under existing offtake agreements. The company currently expects those deliveries to begin towards the end of 2026.

The Delfzijl plant has strategic importance because it is intended to provide commercial validation of Avantium’s YXY technology. The company has previously operated the process at pilot scale in Geleen, but a commercial facility introduces a different set of engineering demands around equipment reliability, process control, maintenance, logistics and sustained operation.

For technology developers, that distinction is fundamental. Laboratory and pilot success demonstrate chemistry and process principles, whereas customers and future licensees need evidence that a plant can be engineered, constructed, commissioned and operated at commercial scale.

The construction record therefore has consequences beyond this single site. Avantium intends the Delfzijl plant to support a wider licensing strategy for future FDCA and PEF production facilities, making start-up performance relevant to prospective partners assessing whether to adopt the technology elsewhere.

The Worley close-out removes one area of uncertainty from that demonstration. Outstanding invoices, claims and responsibility for remediation can continue to affect project cost and management attention after physical construction has largely finished, particularly when a plant enters operation while final contractual positions remain unresolved.

Avantium still faces operational and financial risks. First production has to develop into repeatable output, product must complete qualification, and the company is progressing additional financing while preparing for commercial sales.

The plant has nevertheless crossed several construction and commissioning boundaries in quick succession. Specialist weld remediation has been completed, the main process units have been commissioned, first FDCA has been produced and the principal EPC close-out matters have now been settled.

Attention at Delfzijl is consequently shifting from construction recovery towards plant performance. Further production batches and customer qualification will show whether the facility can move from a successfully commissioned industrial project into the routine commercial operation for which it was built.



  • Greatham flood scheme clears planning for 2027 start

    Greatham flood scheme clears planning for 2027 start

    Environment Agency secures planning approval for £25m Greatham flood scheme. Construction is due to begin in early 2027, combining new defences with major estuary habitat restoration.


  • Finning buys John F Hunt Power Group

    Finning buys John F Hunt Power Group

    Finning acquires John F Hunt Power Group for expansion strategy. The deal adds around 2,500 rental generators, six UK depots, and 145 employees to its power operation.