£15m Naver Bridge project reaches formal completion

£15m Naver Bridge project reaches formal completion

Highland Council has formally completed the £15m Naver Bridge replacement. The new A836 crossing removes a longstanding single-track bottleneck near Bettyhill.


IN Brief:

  • Highland Council has formally completed its £15m replacement of the A836 Naver Bridge near Bettyhill.
  • Wills Bros Civil Engineering delivered the scheme, replacing an 1880s single-track wrought iron crossing.
  • The new bridge began carrying traffic in February before demolition and remaining project works were completed.

Highland Council has formally completed its £15m replacement of the Naver Bridge on the A836 near Bettyhill, bringing the wider construction programme to an end several months after the new crossing first began carrying traffic.

The completed structure replaces a single-track wrought iron plate girder bridge dating from the 1880s. Its removal eliminates a longstanding bottleneck on a route serving local communities in north Sutherland as well as traffic using the North Coast 500.

Wills Bros Civil Engineering delivered the project for the council, supported by Fairhurst and a wider group of suppliers and subcontractors. The formal completion ceremony on 25 September marked the end of the overall project rather than the bridge’s first opening to vehicles, which took place at the end of February.

That distinction reflects the way the replacement was phased. Traffic transferred onto the new bridge once the principal structure and approaches were sufficiently complete, allowing the original crossing to be taken out of service and removed while remaining works continued around the new route.

Demolition of the former bridge began in March. Subsequent activity included completion of the surrounding road works, finishing operations, site reinstatement, and the other tasks required to bring the project through from traffic switch to formal completion.

The replacement had entered its main construction phase in 2024, with early activity including piled foundations, river works, earthworks, and preparation of the new approaches. Building beside an existing crossing allowed the old route to remain available during much of the programme but created its own constraints around working space, river access, environmental protection, and construction logistics.

The original bridge had become increasingly unsuited to the demands placed on the A836. Its single-track arrangement restricted opposing traffic and created a pinch point on a route carrying local, commercial, and tourism movements. Replacing it with a modern crossing increases capacity while reducing dependence on traffic control at the river.

Projects of this type depend heavily on construction sequence. Foundations, abutments, superstructure, barriers, drainage, surfacing, and approach roads must reach a usable condition before traffic can move from the old alignment. Only then can demolition proceed without requiring a prolonged closure or temporary replacement crossing.

That sequence was visible at Naver when vehicles transferred to the new bridge in February. Removing the redundant structure afterwards gave the contractor the space needed to finish the scheme around an operational replacement rather than attempting to complete all demolition and reinstatement before restoring the road connection.

The final project value has been stated at £15m. Earlier council monitoring had identified cost pressure during development, reflecting the extended period between initial planning and construction as well as wider inflation in infrastructure delivery.

The completed cost is substantial for a single rural bridge, but the asset sits on a route where lengthy diversions can magnify the effect of closure or structural restrictions. Highland Council manages an extensive road network containing numerous bridges in remote areas, making resilience and maintainability important alongside immediate traffic capacity.

The River Naver setting also added environmental and temporary works considerations. Foundation construction and activity close to the water had to be planned around the physical requirements of the new bridge while managing the surrounding natural environment and maintaining safe working access.

Remote location affects supply as well as engineering. Concrete, steel, plant, surfacing materials, specialist equipment, and labour must be moved to a site with fewer nearby alternatives than an urban project, while weather and transport conditions can place additional pressure on the programme.

The project also included community activity beyond the main contract. Wills Bros personnel supported work on a footbridge serving Farr Beach, while visits involving local school pupils provided an opportunity to examine civil engineering activity during construction.

Those elements sit outside the principal bridge replacement but illustrate the visibility of major construction in small communities. Compounds, heavy vehicles, river works, traffic management, and route changes can affect day-to-day movement for a prolonged period even where the finished asset occupies a relatively small footprint.

Formal completion closes that period. The replacement crossing is operating, the original bridge has been removed, and the project has transferred from construction into the council’s maintained road network.

Naver is nevertheless one completed project within a much larger bridge and roads investment requirement across the Highlands. The council’s long-term capital programme extends across transport and other public infrastructure, leaving the delivery experience from a remote, environmentally constrained bridge replacement relevant to future structures approaching the end of their serviceable lives.